how to calculate the loads on slab? what are the steps?
Answer Posted / abdul tawaf khan
1) Dead load of slab = 1 * 1 * 25 * D
2) Live load of slab = 1 * 1 * Live load intensity as per IS specifaction
3) Finishing load = 1 * 1 * 24 * t
Where , D = overall depth of slab
t = thickness of floor finish
Also condier Wind load, if any case.
| Is This Answer Correct ? | 2 Yes | 0 No |
Post New Answer View All Answers
What is missing report and how to prepare
dialation means
What is the Unit weight of coarse sand (F.M- 2.20) ?????
Analyze the rate for 1st class brick work in superstructure with 1:6 cement sand mortar. Consider 1000 cu.ft quantity and work out the rate per cu.ft
What are the ingredients of pre-stressed concrete?
Which are the top apps for you civil engineering?
why development length = 50D . why not 100D
How to testing voids of filled aggregate in bitumen mix design
5. Two long boundary walls run parallel to each other at a center to center distance of 1 meter apart. The width and height of the first wall are 0.30 m and 2.5m respectively. While those of the second are respectively 0.18m and 3.5m. Plot the distribution of vertical stress intensity due to walls on a horizontal plane, 1m below ground level. The walls have negligible depth of foundation and are made of brick masonry (y = 19.2 kN/m cu)
what might be the problem faced in the near future if the M-sand is used in the place of river sand during wall plastering? (As per IS)
how to calculate MR 9(derivation)
Why the statue of liberty is made of copper?
In how many types u can do POP on ceiling and walls(on which material or by using which material)? b) what is the difference between dry , oil bound, enamel, acrlyic type of painting? 2nd :- I have certain queries, please help to solve. a) length of pile bore is 4m.excavation quantity will be area * length where area will be pi/4 * dia*dia. Is this right? b) It is a single reamed pile of 300m dia and reamed dia is 750mm. can any body help me to calculate excavated quantity of this bulb(reamed section),, concrete quantity in bulb with showing the formulas to be used?
How we calculate the service time of buildings
in levelling operation the first site on any change point is back site the second site on any change point is fore site the line commenses with fore sight & closes with backsight the line comensses with back sight & closes with fore sigh