Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


how to calculate the strength rebound hammer test if average
reading of 50.6,50.2,49.1,50.5,50.8,51.7 in grade M-60



how to calculate the strength rebound hammer test if average reading of 50.6,50.2,49.1,50.5,50.8,5..

Answer / ronak shah

it is depending upon the graph value which is given in the
is coads. its depnds upon which direction the hammer is
applied. Then after we will do the correction factor.

Is This Answer Correct ?    7 Yes 1 No

Post New Answer

More Civil Engineering Interview Questions

Explain the latest method to detect a crack in a building?

0 Answers  


For 100 bag cement how i will calculate sand and metal aggregate.Mixing proportion 1:1.49:2.38

1 Answers  


what are the types of bridges respective to the span ?

1 Answers  


What should be the Slump(Min.)in cement in concrete in all grades of concrete?

2 Answers  


What is specific gravity & how it is calculated

2 Answers  


what are the ffactors you considered choosing the course?

0 Answers  


WHAT IS DIFFERANCE BETWEN TOR STEEL AND TMT STEEL

4 Answers   BARC, L&T, ONGC,


How to decide/consider the grade of bitumen for dbm.

0 Answers  


24. Why should we hire you?

1 Answers  


1.what is the main responsibilites of Site Engineer ? and what are main attitude ?

3 Answers   UltraTech,


Why can i adopt concreting insted of rubble solling in beds? In comoarision concreting is cheaper than the soling.

1 Answers  


consumption of cement in p.c.c. a. mix. 1:1:2 b. mix. 1:1.5:3 c. mix. 1:2:4 d. mix. 1:3:6 e. mix. 1:4:8

2 Answers   MSPL,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4456)
  • Electrical Engineering Interview Questions Electrical Engineering (16639)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)