why the cube depth is 150 mm which is used for testing
Answer / vinoth kannan
Basically, the force supplied by a concrete compression
machine is a definite value. For normal concrete strength
application, say below 50MPa, the stress produced by a
150mmx150mmx150mm cube is sufficient for the machine to
crush the concrete sample. However, if the designed concrete
strength is 100MPa, under the same force (about 2,000kN)
supplied by the machine, the stress under a
150mmx150mmx150mm cube is not sufficient to crush the
concrete cube. Therefore, 100mmx100mmx100mm concrete cubes
are used instead to increase the applied stress to crush the
concrete cubes
| Is This Answer Correct ? | 14 Yes | 1 No |
Currently how much cost are coming in residential building per sqm with material & Labour rate in Delhi,NCR
How much 1 cum of M15, M20 & M25 concrete weigh?
What are the deshuttering time for Salb Beam Column RCC Wall Footing Staircase
2. In a container filled with each of the following materials, at a porosity of 40%, determine the upward gradient required to cause the quick condition (a) Lead shot with a G = 13.75; (b) Fibre beads with G = 2.15; (c) Sand with a G = 2.32
What is is code for use TOR
I am planning to construction in my plot in Pune (Chandan Nagar) and its near about 1950 SqFt. Can some plz help me on the rate on per sqft for RCC,Brickwork & Plaster,Flooring,Water proofing,Door. Thank you in advance
a sewer which receives the discharge of no. of house sewer is called house sewer lateral sewer intrcepting sewer sub-main sewer
What are the different theories of failure under static load?
Q1) I am having an interview in a construction company for a large sewage project . Since I have not done any such project , there are some queries from my end. Pls. help me to solve them. I will be thankful to you :- a) Normally for large project 400-600 houses & around 1600 peoples , how much dia pipe is used and which type of pipe is used? b) For trenching , I have heard that IS 1200 implies, what are the rules of calculating earthwork in case of depth of 2m or above ? c) To prevent soil to fall when depth of trench is more , what steps are taken and how there qty. is calculated . Like I have heard about timbering . what is this ? d) What are the rules for disposing off the excavated soil ? e) How the pipes that are used are being jointed? f) In case of cleaning on choks , is there any intermediate things provided? g) For foul gases any outlets are provided thru out length of pipeline? h) What is the flow digram like from houses thru small pipe to main pipeline than where main pipeline disposes wastage ? i) Any other thing that has to be kept in mind while calculating earth work for excavation like steps are made and other things? How earthwork is calculated in case of steps ? Pls. explain with a sketch. Regards,
Anyone have sample questions for bhel please send me since Iam appearing for this exam. Kindly send this to my e-mail: nethaj_babu@yahoo.co.in
how many bags of cement required in neat cement finish per square metre
what is the definition of stress& strain.
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)