100 cubic meter of concrete will contain how much amount of
cement, sand and aggregate to form a mix of M15
Answer Posted / channa
1m3 of dry concrete = 1.54m3 of wet concrete
Concrete work to be done=100×1.54=154m3
Cement=(1/(1+2+4))×154=22m3
Wkt, density of cement=1440kg/m3
Mass of cement=1440×22=31680kg
No of cement bags= 31680/50=634bags of cement required
Is This Answer Correct ? | 3 Yes | 0 No |
Post New Answer View All Answers
please what is the number of bars required for a column of 6mx6m and 450mmx300mm,its a commercial building (Church)
Slump Values for works?
What are the responsibilities of a site manager?
detailed calculation of the amount of cement used?
What type of tensile strength is handling by crank in beam? Thanks.
how to calculate total cost for slab 35'×8'
what is Bearing Capacity,How to determine it?
On what basis we decide the formation level of the road? other then that of 50% Cutting and 50% Filling??
what radial pressure, the NP2 class rcc pipe can sustain?
what is the percentage of silt in black cotton soil.?
For the construction project what capital cost has to be taken in consideration?
What are the different methods for drawing an arc?
how to calculate the rebar depth if forgot the foundation reinforcement (main steel)? is that any calculation or formula we have data sheet of supplier what depth what is the pull out capacity is mensioned in data sheet. if any IS code than its help full to me.
States some of the tool bars used in cad?
WHAT IS YOUR CURRENT SALARY