100 cubic meter of concrete will contain how much amount of
cement, sand and aggregate to form a mix of M15

Answer Posted / channa

1m3 of dry concrete = 1.54m3 of wet concrete
Concrete work to be done=100×1.54=154m3
Cement=(1/(1+2+4))×154=22m3
Wkt, density of cement=1440kg/m3
Mass of cement=1440×22=31680kg
No of cement bags= 31680/50=634bags of cement required

Is This Answer Correct ?    3 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

please what is the number of bars required for a column of 6mx6m and 450mmx300mm,its a commercial building (Church)

1391


Slump Values for works?

1859


What are the responsibilities of a site manager?

721


detailed calculation of the amount of cement used?

1713


What type of tensile strength is handling by crank in beam? Thanks.

2152






how to calculate total cost for slab 35'×8'

1585


what is Bearing Capacity,How to determine it?

898


On what basis we decide the formation level of the road? other then that of 50% Cutting and 50% Filling??

2959


what radial pressure, the NP2 class rcc pipe can sustain?

2988


what is the percentage of silt in black cotton soil.?

2045


For the construction project what capital cost has to be taken in consideration?

759


What are the different methods for drawing an arc?

796


how to calculate the rebar depth if forgot the foundation reinforcement (main steel)? is that any calculation or formula we have data sheet of supplier what depth what is the pull out capacity is mensioned in data sheet. if any IS code than its help full to me.

2236


States some of the tool bars used in cad?

773


WHAT IS YOUR CURRENT SALARY

1782