what is the minium content of cementous material per cu
meter
Answers were Sorted based on User's Feedback
Answer / shridhar
The amount of cementitious mateiral is determined by amount
of portland cement plus amount of fly ash.The minimum
portland cement content should be 350 kg/m3 of concrete
| Is This Answer Correct ? | 1 Yes | 1 No |
from where ican get sample papers for CET-delhi 2012
For 1 cu m of concrete required 1.54 Cu m times dry volume. Pl give clarification of 1.54 factor
1 Answers RASA, Unity Infraprojects,
Laboratory experiments conducted in Mumbai on a particular mix showed a strength of 33 MP a for a fully matured concrete. Find whether formworm can be removed for an identical concrete placed at Jammu at the age of 15 days when the average temperature is 60C. The stripping stress in concrete
What is the software used in civil engineering?
What will be the maximum length of RCC Lintels?
Minimum sizes of beam and coloumn
What are the different types of foundation?
I need Bhel engineertrainy test papers in civil engineering please send to email id - hisandy66@gmail.com
for 1sft of Cement plastering ratio 1:3 How much quantity of cement and sand required.?
2 Answers CGL, URC Construction,
For 1 bag cement how i will calculate sand and metal aggregate;Here the mix proportion is 1:2.49:2.38
afe or not
what is the FE415 & FE500?WHAT IS ITS STRENGTH?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)