100 cubic meter of concrete will contain how much amount of
cement, sand and aggregate to form a mix of M15
Answer Posted / yogesh jadhav
m15(1:2:4)
100cum given
wet volume of concrete=30%more than dry volume
=1.3*100=130cum
wastage=20%of wet volume of concrete
=1.2*130=156cum
volume of cement required=156cum/1+2+4=22.28cum
1 bag of cement=35 lit=0.035cum
no of cement bags required=22.28/0.035=636.57=637bags
sand rqd=2*22.28=44.56cum
coarse agg reqd=4*22.28=89.12cum
| Is This Answer Correct ? | 24 Yes | 5 No |
Post New Answer View All Answers
Whats the standard thickness of 20'/30' wide rcc service road and what will be the estimated cost per cubit feet
What are the benefits of rcc pipes over steel designed pipes?
how to workable concrete cube test M-25 design mix
what is yield and tensile strength of steel, if steel has yeilding strength of 60 psi than how much its tensile strength?
why we provide bent up reinforcement bars at l/4 ? if it is because of diagonal shear , how does it acts ?
if i have to draw bending moment diagram of 4 way continous span then how to create it and how to find reaction?
what is the weight of 10mm,20mm,40mm aggregate
What is the standard rate of installing ties for column(60cmx60cm) and beams(50x850)(weight)
sir, whitch is the best book (writer name) for prepration of gate....
specifications of fe500 steel
what is Quantity of stone and sand required for one cubic meter of stone work (UCR)
What is eccentricity in laymans term Can't understand bookish language .please explain in easy way.
how many sqft or cft of work done by a mason per day in all works such as brick,block,concrete,shuttering carpenter,reinforcement fabricator,painter,door window carpenter.....everything thank you
Define What is a projection line?
What is the quantity of cement used for stone pitching work of 100sqm 225mm thick and cement mortar of 1:6? And how?