how much difference we have to provide when column steel staggered
Answers were Sorted based on User's Feedback
Answer / mehul kothari
Lap should be staggered min 1m
But if it is not possible on site condition or you are not able to stood column vertically lap can be provided in between h/4 from top and bottom
If i use easy word to explain you can leave staggerd in middle of column
H/4 should be calculated as clear hight of column
Means h= heiht of slab - thickness of slab - depth of beam
Is This Answer Correct ? | 0 Yes | 0 No |
Lapping Work Explain Briefly
# 1. size of the Bricks # 2. Minimum Crushing Strength of Bricks
What is thumb rule for deep trench excavation
rate analysis of shuttering
What is the difference between shear and tensile strength?
what is the diffrence betwen one way salb & two way salb?
How to calculate sand,cement for 1:5ratio brick masonary
4 Answers IVRCL, Jamek, Prera Nirman Sewa, SPCL,
Design an underground tank of internal dimensions 6m x 3m x 3m. The soil surrounding the tank always remains dry. The tank shall be provided with a roof slab. The soil weighs 16000 N/m3 having an angle of repose of 30.
what is unit of density,specific gravity
what is velocity of approach?
why demand factor less then 1 ?
Weather we heat cement, will it changes its color? if yes why? if no why?