how much difference we have to provide when column steel staggered
Answer Posted / mehul kothari
Lap should be staggered min 1m
But if it is not possible on site condition or you are not able to stood column vertically lap can be provided in between h/4 from top and bottom
If i use easy word to explain you can leave staggerd in middle of column
H/4 should be calculated as clear hight of column
Means h= heiht of slab - thickness of slab - depth of beam
| Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
in one hour , one 200 excavator , how much quantity (mcube)can load ? soil is not hard not soft
How to calculate construction cost of residential building in mumbai
Differentiate first angle & third angle projection?
HOE TO YOU PLAN TO ACCHIEVE THE GOALS?
How to calculate density of 40 mm coarse aggregate, in mixing ration 1:1.5:3? Please explain calculation for density
In Rcc ratio calculation I wanted to know quantity of Steel also.
Define What is rigging?
what is differences between ferrock and concrete ?
what is the maximum number of course that can be laid according to IS code and the max height.
what is the use of water bar in water tank and is this an extra item in estimate?
what is the minimum compressive strength of clay brick
Cement consumption of one cubic meter of aerocon blocks masonry?
WHAT THREE SPECFIC JOB POSITIONS TO YOU TARGET FROM THE COMPANY?
which red: used in roof teping, then use only cement
What is the quantity of cement used for stone pitching work of 100sqm 225mm thick and cement mortar of 1:6? And how?