M10- 1:4:8
Cement = 15.2/1+4+8=1.17 cum
3.4 bag
Sand- .46 cum
Agg. - .92 cum
Is This Answer Correct ? | 6 Yes | 9 No |
57. Calculate the volume of a truck loaded with stone chips whose data are as follows– 5 Top Length - 13-9, 13-10, 13-09 Bottom Length - 13-11, 13-10.5, 13-10 Top width - 8-7.5, 8-8, 8-7 Bottom width - 8-7, 8-8, 8-7.5 Depth - 2-0, 1-11.5, 1-10, 1-11, 1 -10.5, 1-11.75, 1-11
Curing time for 1)R.C.C slab 2)B.W 3)Plastering
Prop carrying load capacity
why we are doing post tensioning in beams and slabs. it is economical compare to rcc? how?
how much cement,sand,aggregate will use for 1 cum in ratio of 1:2:4.
16 Answers ARS, College School Exams Tests, Gulf Construction, HRL, mWorkspace, NCC, URC Construction,
I want to know how much the lapping length for the pilecap reinforcement.. we r using single pile cap which is 24mby54m and 2.5m depth.. total 91piles are supporting the pile cap.. how to do a steel reinforcement??
Cement Co-eff. in block 1:6, brick1:4 work?
What is the percentage of steel in 1cu.m. RCC?
What is the requirement for over all CG of DG from the foundation surface to absorb the vibration of heavy set.
Define Finite element method (FEM)
What is the difference between pvc,cpvc and upvc and where it is used as per their properties?????
what is rolling margin of steel