How many nos. are Contains fly ash Brick in one Cubic meter ?

Answers were Sorted based on User's Feedback



How many nos. are Contains fly ash Brick in one Cubic meter ?..

Answer / anupam nath

474NOS. IF BRICK SIZE IS 230X75X115. IF WE CONSIDER WASTAGE
IT GOES UP TO 485 NOS. BUT REMEMBER FLY ASH BRICKS HAS LESS
WATSTAGE.

Is This Answer Correct ?    14 Yes 2 No

How many nos. are Contains fly ash Brick in one Cubic meter ?..

Answer / satha

qty=0.4*0.2*0.2=.016 say 1/.016 = 62 nos only.

Is This Answer Correct ?    15 Yes 9 No

How many nos. are Contains fly ash Brick in one Cubic meter ?..

Answer / hidayathulla

For any kind of bricks:
you can use this method:- Block size (example). o.4 x 0.2 x 0.2

:- 1cum divided by 0.4 x 0.2+0.012(CM thk)x 0.2+0.012(CM thk)

this answer gives No blocks or bricks

Is This Answer Correct ?    6 Yes 4 No

Post New Answer

More Civil Engineering Interview Questions

How much 1 cum of M15, M20 & M25 concrete weigh?

0 Answers  


what is the weight of a cubic meter of M10 concrete?

5 Answers   L&T,


What is the coeffiencent Friction Angle between Steel and Ashphalt?

0 Answers  


Cement , sand , concrete ration in M30 Grade

1 Answers   ADITI,


An interior designer designed a rack with the given dimensions. The dimensions are in feet. This coplanar frame repeats at every 5feet and constitute a space frame. The total length is 120feet. Which steel member will you suggest? A square bar, A square tube or a circular tube. Explain.

0 Answers  






I have certain queries, please help to solve. a) length of pile bore is 4m.excavation quantity will be area * length where area will be pi/4 * dia*dia. Is this right? b) It is a single reamed pile of 300m dia and reamed dia is 750mm. can any body help me to calculate excavated quantity of this bulb(reamed section),, concrete quantity in bulb with showing the formulas to be used?

0 Answers  


discuss the precautions to be taken during the various steps of manufacturing of concrete

3 Answers  


"how can we find the approximate quantity of materials using in a building or total Expenditure in percentage for rough estimate after known the construction area(sqm)".please if you know something about that please post the answer.

0 Answers  


Which condition will prevail for the design of a swimming pool ? When the pool is empty or when it is filled ?

0 Answers  


how much thickness of roof truss?

1 Answers  


What is meant by cartesian coordinate system?

0 Answers  


HOW MUCH STEEL REQUIRED FOR SLAB OF AREA 23'3"*18.3"? FOR SLAB HOW MUCH DIAMETER BAR WILL USE?

0 Answers   URC Construction,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4452)
  • Electrical Engineering Interview Questions Electrical Engineering (16638)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)