Answer / sana ullah
We konw, Unit weight of cement = 1440 kg/cum
i.e. 1440/3.28^3 kg/cft
= 40.80 kg/cft
1 bag cement = 50 kg,
Then, 1 bag of cement = 50/40.8 = 1.23 cft = 34.72 litres
so none of above given options are correct.
Is This Answer Correct ? | 13 Yes | 2 No |
Answer / engr.asad ali
Answer #3 is correct my first answer is wrong because i was
not concentrated fully on question but the above question is
right when we determined quantity of water with respect to
water cement ration
Is This Answer Correct ? | 0 Yes | 0 No |
Answer / ratheesh
Its Nice Asad Ali.. i like your attitude.. (We can proud we
r a Civil engg)
Is This Answer Correct ? | 0 Yes | 0 No |
Answer / nibas swain
Simple...
1 cum- 1000 lt
1 cum-1440kg
1440kg=1000lt
50kg= 1000/1440*50= 34.72 lt
Is This Answer Correct ? | 0 Yes | 0 No |
Answer / engr.asad ali
Quantity of water in mortar and concrete depend upon on
water cement ratio see
we know that
W/C ratio = Quantity of water
--------------------
Quantity of cement
when W/C ration is 0.54
then
Quantity of water for one bag is 27 lit
when W/C ratio is 0.494
then
Quantity of water for one bag is 24.7 etc
Is This Answer Correct ? | 4 Yes | 6 No |
How to replace dia of bar in beam like 25mm 3no.S at bottom But due to some reason on site 25mm bar is not available Then is it ok to provide 20mm 4no.S? Give description or Formula to calculate area of steel and replacement?
whatis the minimum strength required for M-25 grade concrete in 14days compressive test? What is the procedure of calculation?
What are the applications of modulus of elasticity?
what is the ideal construction joint for slab?
What are the different approaches in designing the floors of the service reservoirs?
what is the theoritical percentage of concrete cubes testing per day?
Strength of brick?
For 1 cu m of concrete required 1.54 Cu m times dry volume. Pl give clarification of 1.54 factor
1 Answers RASA, Unity Infraprojects,
Pls help me to arrive the rates for centering shuttering for highbay using H-frames?
WHAT ARE TYPES OF STRUCTURES
in staad which are the point is to be checked for not fail of structure
The point of contraflexure occurs in