Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


to construct 1450 rft length of 6 feet wall how much cement sand and blocks are required????



to construct 1450 rft length of 6 feet wall how much cement sand and blocks are required????..

Answer / jagan_srinivasan2002@yahoo.co.

L=1450 ft
H-6 ft
Area
1450*6=8700sq.ft (or)808.55 sq.M
Block required for one sq.m-12nos
Total qty of block required -9702.6 say-9700 nos
Cement required is
11 to 15 mgs for sq.m (depending upon the ratio )

Is This Answer Correct ?    0 Yes 0 No

Post New Answer

More Civil Engineering Interview Questions

a butt weld is specified by

0 Answers  


What is grouting? Why it is done?

12 Answers   Gammon,


what is right & short method of measurement of slab&beam

0 Answers   L&T,


Advantage of Aluminum form work in terms of activities can be skip and cost too

0 Answers  


how many cement bags in 1m^3 cement concrete in all grade

8 Answers   Amara Raja,


what is the hanekom repairing material after concreting work

0 Answers   Lafarge,


the distrubution system in water supplies is designed on the basis of avg daily demand peak hourly demand coincident of draft greater of B & C

0 Answers  


What is meant by Anchorage length? Development Length?

10 Answers   HSCC, VHR,


Hi.. Can i get hel in finding HPCL previous year question paper? plz help me in finding thiss..

0 Answers   HPCL,


WHAT TYPE OF MATERIALS (CHEMICALS) ADDED IN CONCRETE TO INCREASE THE STRENGTH OF CONCRETE?

2 Answers  


wht is off shore structure

1 Answers  


How to calculate cement, water, fly ash amount for 1 cum if the w/c ratio is 0.4 and fly ash to cement ratio is 1:9

0 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4456)
  • Electrical Engineering Interview Questions Electrical Engineering (16639)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)