how to creat mix m-20? and how to check shuttering & how is
mark layout at open ground
Answer / ratheesh
M20 = 1:1.5:3
shuttering
1. Slab & beam bottom level should be checked.
2. All props and bracing pipes should be checked,
3. Beam & Slab side alignment should be checked
4. side shuttering plump should be checked,
5. All room dimensions & Openings dimensions should be checked
6. before reinforcement should be apply shuttering oil.
Layout
you should be use pythagoras theorem...
| Is This Answer Correct ? | 2 Yes | 0 No |
1.(a.) how do you calculate the volume of mortar for 1 piece of block 450mm x 225mm x 225mm. (b.) calculate for 1sqm
What are the main reasons for conducting pull-out tests for soil nails?
material used for mendrel use to bend epoxy coated rebar
0 Answers Saudi Aramco Shell Refinery Company SASREF,
WHAT IS THE RATIO OF CEMENT:SAND:COARSE AGGREGADE IN M-20, M-25, M-30, M-35, M-40, M-45, M-50 CONCRETE?
WHAT SHOULD BE THE THICKNESS OF CEMENT M-SAND MIXER IN BETWEEN TWO SOLID CEMENT BRICKS USED FOR A HOUSE WALL?
among the strectcher, header, english and flemish bond which has greater strength? where these bonds are preferred?????
insted of bentonite we can use any alternate material in piling ?
what else we can add rather than admixture in concrete to reduce the cement quantity?
HOE TO YOU PLAN TO ACCHIEVE THE GOALS?
how to calculate the size of triangular ring in rcc column?
0 Answers Prime Perfect Buildcon,
difference between minor and major bridge.
why seismic analysis not done during design of slabs
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)