what are all the pre commissioning activities in WTP in
power plant
Answer / rajan pandey
Raw water pump should be ready by which we can take
water to creator.proper cleaning of aerator,clariflocculator
And storage tank.Dosing system like alugm Dosing,lime dosing,chlorine
dosing should be commissioned.ReadyNess of flocculator.fitting scrapper
Fitting .isolation gate operations should be cheated
| Is This Answer Correct ? | 3 Yes | 0 No |
Looking for Bently Nevada surplus 3300/52-01-00-00 Reverse Rotation Monitor , 4 pieces.
What should be the neutral and body grounding sysytem for grid (132 KV) parallel generators (440 volts)?
What is surging in a centrifugal compressor ? How it occur's ? How is antisurging done ?
LAPT working in alternator / generator
Difference between directional earth fault and non-directional earth fault
What is creep, resilience.
What will happen if id fan on boiler not functioning?.Can the Boiler run without id fan? What is the effect?
How do you consider that you can improve and what assistance do you need to achieve this
what is the real reason than natural draught cooling towers are always in hyperbolic shape
What are the turbine protections.
Where is the pressure reduce valve in the power plant
Calculating Seawater consumption for SWFGD system
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)