what are all the pre commissioning activities in WTP in
power plant
Answer / rajan pandey
Raw water pump should be ready by which we can take
water to creator.proper cleaning of aerator,clariflocculator
And storage tank.Dosing system like alugm Dosing,lime dosing,chlorine
dosing should be commissioned.ReadyNess of flocculator.fitting scrapper
Fitting .isolation gate operations should be cheated
Is This Answer Correct ? | 3 Yes | 0 No |
Qatar Fertiliser Company (QAFCO) Shortlisted me for interview (got the intel from my source) for Field Operator- Utilities post. Please let me know what kind of questions they asked? ... this position requires 5 years of experience in Power Plant and background Diploma in Electrical/ Mech. ... my Background is Electrical and I am a sub Assistant Engineer (Operation) at a private HFO based Power plant... PS: Please Let me know what preparation should I take to obtain the Interview which will be take place In Bangladesh soon
which safety valve will open first if steam is not been supplied to turbine.
I want to build 100 megawatt hydel dam. What does mean, 100 MW per hour? then how many electric bulb of 100 Watts the dam would lit?
difference between vaccum pump and ejector
2 Answers NTPC, Tata Steel Limited,
if suppose boiler has high heavy tube leakage, so in which time we feed the water in a boiler. can we stop the feed water at particular combustion temperature.
What is indipendant power plant
Why superheated are started before I'd and rd fan?
Our 8mw steam turbine (condensing cum extraction) exhaust steam temperature is high even after taken it in hogger why
1 Answers Bombay Rayon Fashions,
Boiler capacity is 5ton, what will be the feed water tank capacity?
11 Answers dscl, Indiabulls, Krest, TCS,
why drum level is increased when one of the running coal elevations are suddenly tripped?
what is scanner air fan & how dose it work & is there any interlock in power plant
why do we use contro fluid tank (cft)in turbo generator area(tg) in power plant?