what are the steps to commissioning a DCS system?
Answers were Sorted based on User's Feedback
Answer / dhanraj suman
1. Panel alignment.
2. Power up DCS with electrical wiring checking.
3. Checking of proper grounding/earthing.
4. Preliminary Electrical I/O testing.
5. Instrumentation Loop checking.
| Is This Answer Correct ? | 36 Yes | 1 No |
Answer / aswini ku sahoo
1-proper allignment of pannel
2 power cable laying from UPS DCDB
3-Checking of proper grounding or earthing
4 Negtive terminal of sup. Vol shuold be zero potential.
and then connect the power cable with proper polarity.
5 U r now almost ready to switch on the pannel but now
one imp thing is to disconnect all AI/AO CARD connector
6 All connector pin should not be sort with the ground.
7 Now swith on the pannel
8 Next UTP cable laying work from DPU TO HMI.
9.Agfter proper connection of UTP ping the system
with priper IP addresss.
10 .now start loop cheching and one by one signal throwing
10.Aftr then one by one
| Is This Answer Correct ? | 2 Yes | 0 No |
I have flow transmiter DP range is 0 to 5000mmwc,(convert) Display to be show in m3/Hr.
What is the difference between Error and Offset.
In control valves (like feed water control valve) we will give 3 kg pressure and how it controls 110 kg of water pressure?
what is a device net.
We are using Rosemount 5400 series Radar Level Transmitters in all types of Sump Applications having oily water hdrocarbon petrochemical nature. What we are facing the problem frequently is that always getting reading frezzed at some value. If we do power recycling , sometimes it is working . then making same freezing problem. If anybody faced before such type of problem and also having solution , Please give the answer.
whats the diff b/w zero pressure and obsolute pressure
what is maxdna ?. explain about the software details.
I have a orifice installed in plant which is design for 0~100 inH2O for 0~80MMSCFD, now due to process change the maximum flow is change to 120 MMSCFD so for this new process value what will be the DP across orifice.
why the steam drum and deaerator level transmitter range is in negative MMWC to zero
3 Answers Emerson, Jindal, JKPM,
Identification of ss fittings, pilot valves, relief valve.
please help me to get the below mentioned quires,which i have to submit for my client.[INSPECTION TEST PLAN] 1]I.T.P for Calibration of all instrument. 2]I.T.P for SS tubing. 3]I.T.P for Fire & Gas devices. 4]I.T.P for CCTV & telecommunication. 5] I.T.P for loop checking.
yogokowa field bus system transmitter all's we are geting IOP fault in Contiunes please help me fine how we can normal the broblems?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)