Answer / shrikant
For avoid the crack between Brickwork and rcc
| Is This Answer Correct ? | 40 Yes | 3 No |
Answer / manoj kumar bhola
To avoid the crack formed due to insufficient gap filling between RCC AND BRICKWORK joint.Therefore we used wire mesh or said as chicken mesh in plastering and also due to this there will a proper bond formation between RCC AND BRICKWORK.
| Is This Answer Correct ? | 28 Yes | 3 No |
Answer / er. ashish sharma
For avoid the cracks between RCC & Brick work & developing
bonding strength in plaster.
| Is This Answer Correct ? | 20 Yes | 3 No |
Answer / sandeep kashyap
because the density of brickwork nd rcc are different so due to this cracks are occurs in between rcc nd brickwork .For avoid the crack between Brickwork and rcc
| Is This Answer Correct ? | 3 Yes | 0 No |
Answer / manseta
We give plastic mesh in place of metal that is plastic re I force mesh. Prevents crack in plasterboard a latter stage
Contact +91 9898 222 222
| Is This Answer Correct ? | 0 Yes | 3 No |
Should vertical shuttering done for CC/ RCC for Damp Proof Course (DPC) be measured?
how to convert cement, sand aggregate quantity from M3 to kg with full description?
Are you good at detailing and explain about the project you have worked on detailing?
How to provide spacer bar in barbending work,parallel to bar or inclined to bar? What is the reason?
How much sand for a 107sqm residensial building
1 Answers Shapoorji Pallonji Group(SPCL),
what do you calaculate PCC/GRADE 10
what do you mean by fe500d what is 500 n what's ,d,
what's the formula for calculate pcc for matt(45mm aggregate)?
concrete mix design for M 30 Grade
What is the bearing capacity of black cotton soil, normal soil and rock?
How do you derive the quantity of cement & sand in brick work construction in 1Meter cube, using CM 1:6 and bricks of size 19*9*9 cm
Pile height is 4.3m. 2nos. under reammer. bulb nose is 75mm and height is 400mm. pile dia is 375mm and overall dia 940mm.pls. help to calculate concrete in pile and bulbs separately. What is formula for bulb volume calculation ?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)