What is the construction cost per sq foot for residential
building and give bifurcation of same?
Answer / khadar babu
Sr. No. Contract Code and Name Cost per Sqfoot % of total cost
A. Consultants
1 Architectural desigining 21.85173 1.2
2 Structural desigining 7.283911 0.4
3 Services 13.11104 0.7
7 Model making 1.098774 0.1
9 Plot Survey 0.137347 0.0
Total 43.83311 2.4
B. Civil Works
1 Excavation 15.96403 0.9
2 Antitermite treatment 0.106861 0.0
3 Sub structure Waterproofing, 3.965101 0.2
4 RCC works, Blockwork, Plaster, Misc civil works
966.7697 52.0
Total 986.8057 53.1
C. Finishing Works
1 FLOORING 142.01 7.6
2 Kitchen Platform with Sink 21.41376 1.2
3 Entrance lobby & signage 9.15645 0.5
4 Wood works 67.81992 3.6
5 Waterproofing 12.74205 0.7
6 Gypsum Plaster 36.52273 2.0
7 P.O.P false ceiling 6.498941 0.3
8 External Painting 20.82378 1.1
9 Internal Painting 21.26266 1.1
10 staircase painting 1.912218 0.1
11 Lift Shaft Painting 0.345885 0.0
12 Duct Painting 2.53158 0.1
13 Ceiling paint 7.623122 0.4
14 Aluminum Window 46.1979 2.5
17 M.S Railing 11.16349 0.6
18 Façade work 6.190976 0.3
Total 419.6929 22.6
D. Services
1 Plumbing& pumping 51.57279 2.8
2 CP Sanitary (Jaquar & Roca) 44.45325 2.4
3 Firefighting 23.43493 1.3
4 Electrical 76.44474 4.1
5 Lifts 82.40805 4.4
6 IBMS 16.33613 0.9
7 Solar water system 4.395096 0.2
8 DG Set 6.592644 0.4
Total 305.6376 16.4
Initial Total (A+B+C+D) 1755.969 94.4
Site eastablishment 33.01863 1.8
Electrical & water charges 1.5% 26.33954 1.4
Contingenices for temp. works 17.55969 0.9
EHS budget 8.779847 0.5
Construction Cost / Sft 1859.227 100.0
| Is This Answer Correct ? | 3 Yes | 0 No |
How much time Required for PPR pipe network testing
what"s the purpose of damp proof course (DPC)and where it"ll provide?
What is modular elasticity?
what is the grade of 1:2:1 concrete mix
Give open excavation details of Building.
What is the difference in painting using Roller and Brush? What is the paint consumption difference? As per IS one coat of painting is painting from left to right and top to bottom whether this can be done using roller ( Roller Stick height and feasibility) ?
what are the major benefit in auto level?
Which is the direction of negative angle?
in 1:4,1:6 and 1:8 cement mortar mix how much water required? and find water cement ratio?
What is difference between limit state and working stress method? How it is applies in building structure.
rate analysis,what is PERT, TMT ,UPVC
How to calculate chejja reinforcement
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)