Sr. No. Contract Code and Name Cost per Sqfoot % of total cost
A. Consultants
1 Architectural desigining 21.85173 1.2
2 Structural desigining 7.283911 0.4
3 Services 13.11104 0.7
7 Model making 1.098774 0.1
9 Plot Survey 0.137347 0.0
Total 43.83311 2.4
B. Civil Works
1 Excavation 15.96403 0.9
2 Antitermite treatment 0.106861 0.0
3 Sub structure Waterproofing, 3.965101 0.2
4 RCC works, Blockwork, Plaster, Misc civil works
966.7697 52.0
Total 986.8057 53.1
C. Finishing Works
1 FLOORING 142.01 7.6
2 Kitchen Platform with Sink 21.41376 1.2
3 Entrance lobby & signage 9.15645 0.5
4 Wood works 67.81992 3.6
5 Waterproofing 12.74205 0.7
6 Gypsum Plaster 36.52273 2.0
7 P.O.P false ceiling 6.498941 0.3
8 External Painting 20.82378 1.1
9 Internal Painting 21.26266 1.1
10 staircase painting 1.912218 0.1
11 Lift Shaft Painting 0.345885 0.0
12 Duct Painting 2.53158 0.1
13 Ceiling paint 7.623122 0.4
14 Aluminum Window 46.1979 2.5
17 M.S Railing 11.16349 0.6
18 Façade work 6.190976 0.3
Total 419.6929 22.6
D. Services
1 Plumbing& pumping 51.57279 2.8
2 CP Sanitary (Jaquar & Roca) 44.45325 2.4
3 Firefighting 23.43493 1.3
4 Electrical 76.44474 4.1
5 Lifts 82.40805 4.4
6 IBMS 16.33613 0.9
7 Solar water system 4.395096 0.2
8 DG Set 6.592644 0.4
Total 305.6376 16.4
Initial Total (A+B+C+D) 1755.969 94.4
Site eastablishment 33.01863 1.8
Electrical & water charges 1.5% 26.33954 1.4
Contingenices for temp. works 17.55969 0.9
EHS budget 8.779847 0.5
Construction Cost / Sft 1859.227 100.0
| Is This Answer Correct ? | 3 Yes | 0 No |
Post New Answer View All Answers
How much form and scaffolding per cubic meter volume of concrete class ''A'', ''B'', and ''C''
For The preparation of goverment examination Which book i will prefer and by which way i will do the preparation for exam.
how many monpower required for 1 sqm normal RCC structure ( includes finishes & MEP )
How to calculate the force on a column of three story building. What should be the base concrete height?.
how to calculate Rate of analysis for 100 m3 Any ratio of concrete ? including labour
An interior designer designed a rack with the given dimensions. The dimensions are in feet. This coplanar frame repeats at every 5feet and constitute a space frame. The total length is 120feet. Which steel member will you suggest? A square bar, A square tube or a circular tube. Explain.
TELL ME THE EQUATION FOR OGEE SPILLWAY
what is the mode of method of face bar measurement
what is the type of earthing
Questions related to civil.engg in company
What is the difference between Grade I, II and III of GSB?
What is the Systematic Responsibility Site Engineer? Who are the above and under co-oridinating ? What is office & Site co-ordination of Site Engineer?
A rock anchor 3 1/2” in diameter is placed in rock. The which has an allowable shear strength of 1200 psi. Determine the required anchorage length to safely carry a 80 ton load using a 2.0:1 F.S
CAST EFFECTIVE WATER SUMP CONSTRUCTION DETAIL
For sloping slabs or sloping beams why the tension steel from either side of ridge is taken into compression zone of other side?