What is the construction cost per sq foot for residential
building and give bifurcation of same?
Answer Posted / khadar babu
Sr. No. Contract Code and Name Cost per Sqfoot % of total cost
A. Consultants
1 Architectural desigining 21.85173 1.2
2 Structural desigining 7.283911 0.4
3 Services 13.11104 0.7
7 Model making 1.098774 0.1
9 Plot Survey 0.137347 0.0
Total 43.83311 2.4
B. Civil Works
1 Excavation 15.96403 0.9
2 Antitermite treatment 0.106861 0.0
3 Sub structure Waterproofing, 3.965101 0.2
4 RCC works, Blockwork, Plaster, Misc civil works
966.7697 52.0
Total 986.8057 53.1
C. Finishing Works
1 FLOORING 142.01 7.6
2 Kitchen Platform with Sink 21.41376 1.2
3 Entrance lobby & signage 9.15645 0.5
4 Wood works 67.81992 3.6
5 Waterproofing 12.74205 0.7
6 Gypsum Plaster 36.52273 2.0
7 P.O.P false ceiling 6.498941 0.3
8 External Painting 20.82378 1.1
9 Internal Painting 21.26266 1.1
10 staircase painting 1.912218 0.1
11 Lift Shaft Painting 0.345885 0.0
12 Duct Painting 2.53158 0.1
13 Ceiling paint 7.623122 0.4
14 Aluminum Window 46.1979 2.5
17 M.S Railing 11.16349 0.6
18 Façade work 6.190976 0.3
Total 419.6929 22.6
D. Services
1 Plumbing& pumping 51.57279 2.8
2 CP Sanitary (Jaquar & Roca) 44.45325 2.4
3 Firefighting 23.43493 1.3
4 Electrical 76.44474 4.1
5 Lifts 82.40805 4.4
6 IBMS 16.33613 0.9
7 Solar water system 4.395096 0.2
8 DG Set 6.592644 0.4
Total 305.6376 16.4
Initial Total (A+B+C+D) 1755.969 94.4
Site eastablishment 33.01863 1.8
Electrical & water charges 1.5% 26.33954 1.4
Contingenices for temp. works 17.55969 0.9
EHS budget 8.779847 0.5
Construction Cost / Sft 1859.227 100.0
| Is This Answer Correct ? | 3 Yes | 0 No |
Post New Answer View All Answers
A roof has a U value = 0.65 W/m2 .C. Extra insulation is to be provided. This insulation has a thermal resistance = 1.5 m2"C/W. Calculate the new improved U value.
How we can calculate the cement, sand,bricks , water , quintity in 1:6 Ratio 1 cubic metre b/w and 1:4 Ratio in 1 Squre metre b/w????
Moisture content calculation for diff mix ratio's ??
what is the effect of duration of earth quake on framed structures ?
How many lbs are there in a yard?
In how many types u can do POP on ceiling and walls(on which material or by using which material)? b) what is the difference between dry , oil bound, enamel, acrlyic type of painting? 2nd :- I have certain queries, please help to solve. a) length of pile bore is 4m.excavation quantity will be area * length where area will be pi/4 * dia*dia. Is this right? b) It is a single reamed pile of 300m dia and reamed dia is 750mm. can any body help me to calculate excavated quantity of this bulb(reamed section),, concrete quantity in bulb with showing the formulas to be used?
manhole height is 1500 mm and width of brickwork is 230 mm dia of manhole covering is 560 mm brick masonry 1:4 horizontal length is 1500 mm and plaster 12 mm thick on both side 1:3. how to estimate the quantity of brickwork with mortar cement and sand for manhole chamber.
Explain the different types of roofing systems?
1) write Short notes about Shellow & Deep well? 2) What is the full form of SPT & SMB? write short notes. 3) write short notes about efficiency of Riveted joint.
i have applied 40mm spacer in the concrete for tie beam. is it correct? kindly give me if there any code available
What is GSB gradation
What is meant by solid geometry?
What is labor and material payment bond?
How to find permissible diagonal tensile stress in reinforced brick work
Discuss some applications of modular elasticity?