I need to know the productivity of meason/labour/barbender/carpenter while doing work like Shuttering, reinforcement steel, brick work, earth work?
Answer / javed
1) Excavation over areas (hard/dense soil),depth up to 1.5m and removal (up to one meter from edge)
M3
Mate
Labour
0.06
0.62
_
_
2) Excavation in trenches (soft/ loose soil),for foundations not exceeding 1.5m in width and for shafts, wells, cesspits and the like, not exceeding 10m3 and on plan, depth up to 1.5m and removal(up to one meter away from edge)
M3
Mate
Labour
0.05
0.50
_
_
3) Returning, filling and ramming of excavated earth in layers not exceeding 20 cm in depth, watering, well ramming and leveling, lead up to 50m
M3
Mate
Labour
Bhisti
0.02
0.25
0.02
_
_
_
4) Concrete :
Mixing by machine (mixer) at banker, cement concrete (with 20mm graded coarse aggregate)
M3
Labour
Bhisti
Mixer operator
Mixer
0.50
0.10
0.07
0.07
_
_
_
_
5) Mixer mixed cement concrete
M3
mason
Labour
bhisti
mixer operator
mixer
vibrator
0.10
1.63
0.70
0.07
0.07
0.07
_
_
_
_
_
_
6) Reinforced cement concrete in situ in foundations, footings, bases for columns, etc excluding form work and reinforcement
M3
mason
Labour
bhisti
mixer operator
mixer
vibrator
0.17
2.00
0.90
0.07
0.07
0.07
The constants for items include mixing, pouring, consolidating and curing. This does not include fair finish.
7) Reinforced cement concrete in situ in suspended floors/roofs excluding form work, and reinforcement.
M3
mason
Labour
bhisti
mixer operator
mixer
vibrator
0.24
2.50
0.90
0.07
0.07
0.07
_
_
_
_
_
_
8) Mortars :
Mixing by hand, cement mortar of any mix/proportions
M3
Labour
Bhisti
0.75
0.07
Labour required will be approximately same for different mix proportions.
9) Brick work (straight walls) :
Brick work in walls exceeding one brick thick, in cement / lime mortar
M3
mason
Labour
bhisti
0.94
1.80
0.20
The constants include labour involved in scaffolding.
10) Brick work in walls, one brick thick, in cement/lime mortar
M2
mason
Labour
bhisti
0.25
0.40
0.10
The constants could be adopted for brick work with any mix or mortar.
11) Formwork :
a) fabrication and erection with all supports, struts, braces, etc, and dressing with oil as cleaning of formwork :
1) rectangular column and walls
2) suspended floors/roofs
3) sides and soffits of beam
M3
M2
M2
Carpenter
Labour
Carpenter
Labour
Carpenter
Labour
0.25
0.20
0.23
0.20
0.30
0.20
_
_
_
_
_
_
12) Reinforcement:
Bar reinforcement including cutting to length, hooked ends, cranking or bending, hoisting and placing in any position, binding wire and holding firmly so as not to be disturbed while placing and ramming of concrete
Quintal
Bar bender
Labour
1.00
1.00
_
_
13) Plastering and pointing :
a) 15mm thick cement plaster to ceiling including mixing of mortar.
b) 15mm thick cement plaster on brick walls (exterior) including mixing of mortar
c) Tuck pointing to random rubble masonry in cement mortar including mixing mortar.
M2
M2
M2
mason
Labour
bhisti
mason
Labour
bhisti
mason
Labour
bhisti
0.08
0.10
0.10
0.06
0.10
0.10
0.10
0.15
0.10
_
_
_
_
_
_
_
_
_
14) Damping proof course :
a) Laying damp proof course 40mm thick cement concrete including form work and fair finishing to edges and mixing.
M3
Mason
Labour
bhisti
0.10
0.10
0.01
| Is This Answer Correct ? | 0 Yes | 0 No |
what is the formula to calculate costing of rubble soling and wbm in road works?
What are the standard plastic limit/liquid limit/plasticityindex for differrent type of soils?
I've one slab of 24m x 43m. How to calculate required steel For this slab.
How many cover blocks should be provided for 10 sq.m area?
Difference between Hydro Pneumatic and Gravity system of water supply in a building?
WHICH KIND OF ADDITIONAL PILE DRIVEN TO INCREASE THE CAPACITY OF SUPPORTING LOADS ON VERTICAL PILES
For the calculation of bearing pressure below the footing, to know whether it is below the safe bearing pressure of the soil, the unit of RCC below ground level to be taken is 25 KN/m3 or (25-15)KN/m3, where 25 is the unit weight of RCC and 15 is the unit weight of soil and whether the weight of backfilling to be taken?
What is the accepted silt content in sand for concreting purpose by volume method?
What are the basic use of runners and standards of pipelines?
what is the formula of calculating number of bars?
For Granite Flooring,For Cement Slurry purpose which one is effective of cost control whether OPC or PPC or White cement?
what is grade intersection?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)