at first volume i.e lenght ,breadth , hieght
den for eg.
a) For 1 m3 of concrete Mix 1:2:4 (M15)
Add 50% for wet concrete = 1.50 m3 or 1.52 m3 or1.55 m3
= 1.50/(1+2+4) = 0.214 m3
For 1 m3 = 30 bags of cement required (1440/50) say 30 bags
Cement = 0.214 x 30 = 6.42 bags
Sand = 0.214 x 2 = 0.428 m3
Aggregate = 0.214 x 4 = 0.856 m3
| Is This Answer Correct ? | 8 Yes | 4 No |
How much quantity of water required for curing of: 1) For concrete of 10cu-m or 10sq-m 2) For blockwork of 10sq-m 3) For plastering of 10sq-m
minimum dia of manhole cover should be A] 50 cm B ] 100 cm C ] 75 cm
Material calculation of cm 1:6 for 1sqm
.5Ast
what type of cement are used for fixing of tiles at floor/wall
what does '415' in FE415 stands for??
how many brick in 1 cubic meter with mortar ?
how much cement consumption in 1 sqmt of wall cleading work (dedo)?
What is the spacing of chairs in reinforcement steel.If it is written in IS 456:2000 then tell me the page number.
how many pcs of steel bundule in all dia 8,10,12,16,25,32,40 please how many pcs in bundle of packing??
How you calculate cement,sand,20mmbluemetal,40mmbluemetal,bricks for various works
Kindly post me previous year interview questions with answer for post of Manager (civil engg.) for NTPC, IOC , GAIL etc. I have interview on july 2013.I will be very grateful to you. Please guide me.
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)