what would be the rqmnt. of cement and sand (1:6)for
building brick wall and also 20mm thick plaster on the wall
by same ratio?
Answer Posted / p.rambabu
1.approximately we can calculate the requirement of brick
work for 1cum of 1:6 ratio
ans:cement=(1/6)*1440=239.999*0.21=50.399/50=1.007bags/cum.(here
the ratio of 0.21is the approximately dry volume of sand).
2.for 20mm thk plastering calculation,
a.first we can calculate the volume of plastering area,
b.increase it's volume to 20% because of the honeycomb
work& miscellaneous works.
c.multiply this value with dry volume of 1.3.
for 1:6 for 20mm thk of 100sq.m
cement=(1/7)*1.3*2.2=0.408*1440=587.52/50=11.750bags.
| Is This Answer Correct ? | 2 Yes | 3 No |
Post New Answer View All Answers
What is the likely strength of a 1:2:4 concrete mix?
There are two buildings one taller and one shorter whose time period will be grater and similarly the frequency ?
HOW TO CLACULATE CEMENT AND SAND CONSUMPTION FOR THE STAIRCASE KOTA FLOORING IN THE RATIO OF 1:4 50 MM THICKNESS
how to calculate number of bitumen for road asphalt
why is M25 and Fe 500 assumed to be most economical? i feel it is not.This is because higher grade of concrete and steel has higher lapping length and anchorage length compared to lower grades..
2. In a container filled with each of the following materials, at a porosity of 40%, determine the upward gradient required to cause the quick condition (a) Lead shot with a G = 13.75; (b) Fibre beads with G = 2.15; (c) Sand with a G = 2.32
I have an span length 16 ft c/c
In block work seawalls what is the purpose of slip joints?
what might be the problem faced in the near future if the M-sand is used in the place of river sand during wall plastering? (As per IS)
if the nitrates more than 45mg/l in water lead to disease then what is it called
Moisture content calculation for diff mix ratio's ??
WHAT THREE SPECFIC JOB POSITIONS TO YOU TARGET FROM THE COMPANY?
660 square fit two story house make totally how much cement, sant, brick,aggregate, steel totally how much need
In csae of hume pipes NP stands for Non Pressure bur what does it really mean?
Anyone have sample questions for bhel interview.please send me as Iam appearing for the interview on 19th sep2008. Kindly send this to my e-mail: arun_prasath_n@yahoo.co.in