Answer / r.k sharma
IS code 456-2000 states that Forms shall not be released until
the concrete has achieved a strength of at least twice the
stress to which the concrete may be subjected at the time of
removal of formwork (para 11.3).Minimum Period Before Striking
Vertical formwork to columns, walls, beams is 16-24 hours.
CC/RCC for DPC on plinth is never subject to any stress and
meant for retaining the material till Cement sets.As such it
should not be measured separately and treated as incidental to
the Work of DPC.
Is This Answer Correct ? | 6 Yes | 0 No |
Answer / anupom
Above answer is right, also
THe thickness of DPC is very less(apprx. 25mm) and is
generally applied as a coating layer for plinth level. Thus
the vertical shuttering may not be measured but this solely
depends on the contract specification.
Is This Answer Correct ? | 3 Yes | 0 No |
What is value of S.F at Point of contaflexure?
How its coming concrete grade M 20 means 1:2:4. how it coming 1:2:4.
What is the meaning and full form of FTA and MTA in plumbing material
sir when can we expect the AEE results and when will be the interviews sheduled please guide us in this regard thanking you
For Beam steel reinforcement detailing, in the End of the beam do the making of L shape in the rebar is essential in all the cases, specially in the ends of the Beam?
in 1:4,1:6 and 1:8 cement mortar mix how much water required? and find water cement ratio?
What is construction joint and expansion joint in CC pavements
Is it worthwhile to carry out tests on particle density of soil particles for geotechnical design?
GIVE US DETAIL OF YOUR PRESENT EMPLOYMENT STATUS?
Quality control
what is the mix design for M:60 with micro silica andmetakaoline?
how to calculate rate analysis for shuttering of waffle slab