Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


Should vertical shuttering done for CC/ RCC for Damp Proof
Course (DPC) be measured?

Answers were Sorted based on User's Feedback



Should vertical shuttering done for CC/ RCC for Damp Proof Course (DPC) be measured? ..

Answer / r.k sharma


IS code 456-2000 states that Forms shall not be released until
the concrete has achieved a strength of at least twice the
stress to which the concrete may be subjected at the time of
removal of formwork (para 11.3).Minimum Period Before Striking
Vertical formwork to columns, walls, beams is 16-24 hours.
CC/RCC for DPC on plinth is never subject to any stress and
meant for retaining the material till Cement sets.As such it
should not be measured separately and treated as incidental to
the Work of DPC.

Is This Answer Correct ?    6 Yes 0 No

Should vertical shuttering done for CC/ RCC for Damp Proof Course (DPC) be measured? ..

Answer / anupom

Above answer is right, also
THe thickness of DPC is very less(apprx. 25mm) and is
generally applied as a coating layer for plinth level. Thus
the vertical shuttering may not be measured but this solely
depends on the contract specification.

Is This Answer Correct ?    3 Yes 0 No

Post New Answer

More Civil Engineering Interview Questions

what is rebaring?

2 Answers   SSC,


please give me the rates of RCC(CUM), PCC(CUM), Brick Work(CUM), Tile Flooring, Saria Shuttering

0 Answers  


how to determine the foundation footing reinforcement spacing

0 Answers  


say you are requsituoning cement to build masonry wall made of burnt clay bricks. how many 50 kgs cement bags will you requisition for 1:5 ratio mortar joint, if they masonry wall volume is 10 m3

1 Answers  


How should we design a brick column and footing?(note: no reiforcement to be provided) Can you tell me any reference book where i could possibly find this design? Plz help urgently

0 Answers  


how to find quantity for binding wire steel.

6 Answers   Lanco,


what is the specific gravity of rubble in plum concert

0 Answers  


List out the diameter of series of bar for beam, column, slab and footing?

5 Answers  


Pile height is 4.3m. 2nos. under reammer. bulb nose is 75mm and height is 400mm. pile dia is 375mm and overall dia 940mm.pls. help to calculate concrete in pile and bulbs separately. What is formula for bulb volume calculation ?

0 Answers  


what is the formula to find the diagonal shape stirrups?

0 Answers  


What is the ratio of cement ,sand, and aggregate to be used in M20 grade of concrete when excavating 200 x 200 x 200 mm of sand from soil

4 Answers  


length where bent up is made in slab of bridge from one end

0 Answers   NTPC,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4453)
  • Electrical Engineering Interview Questions Electrical Engineering (16638)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)