In BoM i mentioned item category as L But when i create po
for sub-contracting defaultly it shows T, I dont understant
where i done mistake, can you help me please by sadeesh
Answers were Sorted based on User's Feedback
Answer / satish
Hi Siva
BOM ELEMENT DEALS WITH MM; PP and SD modules so it is not
only MM or SD
When you create subcontract the T- CODE to be used is M21N
and the order type is NB the reason why the Item category
changed to T or M instead of L is based on the Typs of
Material you are using . It wil be l if the material is a
not stock material Else will come to the material category
However you need not delete BOM . just change the
material category to NON stock and will get the required
item category
Is This Answer Correct ? | 4 Yes | 0 No |
Answer / shiva
Its not your problem, actually from sd people.
go to BOM delete the items and create a new one there
Is This Answer Correct ? | 5 Yes | 4 No |
Answer / rajesh
another process is u can directly go to me21n and item
category as "L" and go to item overview there in one tab
you contain "components" icon plz click that and give the
materials there what are the materials for subcontract
Is This Answer Correct ? | 1 Yes | 0 No |
what r the priority levels used in SAP, r these defined by individual companies r set same fr all
What is the lot size attribute of a material?
you create a PO,for 100 qty and enter GR for 100 qty but IV for 80 qty it is possible or not? If it is possible how.
Explain the 're-order point' procedure?
What is release procedure?
What are the key fields for the material master?
How to procure 2 laptops of the same quality with 2 different prices to 2 different plants p1 and p2 of the same company? How will you map this process using SAP MM?
3 Answers Cap Gemini, Deepak Fertilisers, Reliance, Tech Mahindra,
For creating a purchasing info record what are the pre-requisites?
what is the transaction code used to extend the material view?
What controls the order in which the approval must take place?
Is it possible to activate split valuation after posting several transaction for materials?
What is Purchase Requisition means? Why we used this in MM Module in SAP? what is t.code of it?