binding wire requirement in rcc structures
Answers were Sorted based on User's Feedback
Answer / santosh singh
about 9 to 13 kg of binding wire is required per ton of
steel
| Is This Answer Correct ? | 10 Yes | 6 No |
Answer / saalim
1 to 1.5 kg per quintal
ie 10 to 15 kgs per tonne depending upon dia of steel.
| Is This Answer Correct ? | 6 Yes | 2 No |
How do we calculate absolute pressure?
What is the Null Point of chimney in Power Plant
Define What is passive earth pressure ?
Briks type
For removal of formwork of simply supported slab / beam from where to start the deshuttering? ( Max Bending moment of the simply supported beam is in the center hence is it required to start from the supports?)
How to calculate density(dry & bulk) of sand from Sp. ravity value of sand. eg. G=2.5
I Want To Know Quantity of Cement Conc. & Sand in Column of 9"x9"x10'
0 Answers Ajai Builders, Malhotra Associates,
why we used shahabad stone (ladi) in box type water proofing.what is the main roll of shahabad stone?
1 cubicmeter liquid = how much litre
if water absorption is more than 25 percent in brick, what is the defect in it?
What is the mix propotion of M10,M15,M20,M25,M30,M40,M50.M60 cement content,aggrigate,sand and water ratio.
How much quantity of cement and sand required for the inlining of 610mm dia MS pipe 8.7mm thk.Inlining thickness is 10mm and CM ratio is 1:1.5.
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)