You are implementing a sap project. implementation compled
and development started and at that time you found that
there is major problem with the system .It would take again
time and customer is not happy with that ,in that case how
do you convince customer?
Answers were Sorted based on User's Feedback
Answer / gali lakshmi prasad
Say honestly "apologies" / "sorry" for dealy, and also
mention that you always strive to achieve customer's
delight, probably quote past excellent customer ratings, in
case it is proper. Talk to customer confidently that you
need a certain time to rectify the problem, and mention
that your team is already in RRCA(Relentless Root Cause
Analysis). Submit this RRCA to customer after completion of
the main project.
But remember while escalating to customer, please don't
blame the your organisation system, employees, facilities,
or working hours, these all mean a lot negetiveness.
| Is This Answer Correct ? | 28 Yes | 4 No |
Answer / harish gaggar
1) Try to find root cause of problem, also invite team member suggestion.
2) Try workaround
2) Check if this issue included in Risk register or not. If yes there should be mitigation plan for that.If not PM should register this issue first and try to place Contingency plan or fallback plan.
3) Prepare impact analysis
This is steps just to make sure PM should be ready with PM plan and technical analysis before presenting to management and customers to get their buy in and necessary approval for change in schedule baseline.
| Is This Answer Correct ? | 11 Yes | 1 No |
You have been asked to submit a proposal for a project that has been put out for bid. Prior to submitting the proposal, your company must register so that their firm is on the qualified seller list. Which of the following is true? A. The qualified seller list provides information about the sellers and is a tool and technique of the Solicitation process. B. The qualified seller list provides information about the project and the company that wrote the RFP and is an input to the Solicitation process. C. The qualified seller list provides information about the project and the company that wrote the RFP and is a tool and technique of the Source Selection process. D. The qualified seller list provides information about the sellers and is an input to the Solicitation process.
You are in the Planning process of your project, and your project sponsor has requested an accurate cost estimate in two weeks from today. You'll use which of the following techniques to provide her with the most accurate cost estimate? A. Bottom-up B. Analogous C. Top-down D. Earned value
Explain on the project management life cycle process?
How do you motivate team members?
Which of the following is displayed as an S-curve? A. Gantt B. Cost baseline C. Critical path D. PERT
You are a project manager for Laredo Pioneer’s Traveling Rodeo Show. You're heading up a project to promote a new line of souvenirs to be sold at the shows. You're ready to write the scope statement, and you know it should contain which of the following? A. Project justification, benefit/cost analysis, project deliverables, and product analysis B. Product analysis, project product, and project deliverables C. Project justification, project product, project deliverables, and project objectives D. Product analysis, project deliverables, benefit/cost analysis, and project objectives
what do you do after a milestone is completed?
Which of the following is true regarding the scope statement? A. It describes how to make changes to project scope. B. It describes project deliverables and serves as a baseline for future project decisions. C. It assesses the stability of the project scope and is a baseline for future project decisions. D. It assesses the reliability of the project scope and describes the frequency of changes and their impacts.
You are the project manager for a construction company that is building a new city and county office building in your city. Your CCB recently approved a scope change. You know that scope change might come about as a result of all of the following except: A. Schedule revisions B. Product scope change C. Changes to the agreed-upon WBS D. Changes to the project requirements
You are a project manager for Laredo Pioneer’s Traveling Rodeo Show. You’re heading up a project to promote a new line of souvenirs to be sold at the shows. You need to gather the inputs to write the scope statement. You gather which of the following? A. Project charter, product description, assumptions, and constraints B. Project charter, product analysis, and cost benefit analysis C. Product description, product analysis, and project charter D. Product description, assumptions, constraints, and product analysis
Your project was just completed. Due to some unfortunate circumstances, the project was delayed causing cost overruns at the end of the project. Which of the following is true? A. You document the circumstances as lessons learned. B. You pay particular attention to archiving the financial records for this project. C. Your project ended due to starvation because of the cost overruns. D. You document the circumstances surrounding the project completion during the Scope Verification process.
You are working on a project to develop a new website for your company. You are monitoring results of the project to determine if they comply with standards set out during the Planning processes. You are also taking steps to eliminate unsatisfactory results. This might mean rework in some cases. Which process are you in? A. Risk Monitoring and Control B. Quality Control C. Integrated Change Control E. Scope Change Control