Common causes of variances are a result of all of the following except:
A. Random variances
B. Predictable variances
C. Special variances
D. Variances that are always present in the process
No Answer is Posted For this Question
Be the First to Post Answer
You know that PV = 475, AC = 430, EV = 480, EAC = 40, and BAC = 525. What is VAC? A. 440 B. 390 C. 485 D. 435
Performance reporting tools and techniques include all of the following except: A. Earned value analysis B. Statistical sampling C. Variance analysis D. Performance reviews
Your project depends on a key deliverable from a vendor you've used several times before with great success. You're counting on the delivery to arrive on June 1. This is an example of : A. Constraint B. Objective C. Assumption D. Goal
Integrity in the project management field is accomplished through all of the following except: A. Training to learn how to manage relationships with others from different cultures B. Adhering to an ethical code C. Applying established project management processes D. Following the Project Management Professional Code of Professional Conduct
Your team is split between two buildings on either side of town. As a result, the team isn't very cohesive because the members don't know each other very well. The team is still in the storming stage because of the separation issues. Which of the following should you consider? A. Corrective action B. Collocation C. Training D. Conflict resolution
You are the project manager for a new construction project in your city. Your longtime personal friend is bidding on the project. They've asked you to give them an indication of the budget for this project so that they do not overbid and lose the deal. What is the most appropriate response? A. Give the information to your friend. You know their character and can trust that they won't tell anyone. B. Tell your friend that after all this time, they should know you better than to think you'd put your personal integrity on the line or compromise your job due to a conflict of interest. Decline to give them the information. C. Tell your friend you'll give them the information if they'll promise not to tell anyone and if they'll agree to help you out with some materials on your basement-refinishing project. D. Give the information to your friend and inform the project sponsor so that the information can be shared with the other bidders as well.
All of the following strategies are tools and techniques of Risk Response Planning used to reduce or control risk except? A. Mitigation B. Simulation C. Avoidance D. Acceptance
You are a project manager for Laurel's theater productions. Your new project is coming in over budget and requires a cost change through the cost change control system. You know all of the following are true regarding Cost Control except: A. Performance is monitored to detect variances B. Changes are reflected in the cost baseline C. Changes are monitored and reflected in the project scope D. Changes are monitored so that inappropriate changes do not get into the cost baseline
What are the outputs of the Scope Planning process? A. Product analysis, scope statement, and scope management plan B. Scope statement, scope management plan, and WBS C. Scope statement, supporting detail, and WBS D. Scope statement, supporting detail, and scope management plan
If your expected value is ll0 and the standard deviation is l2, which of the following is true? A. There is approximately a 99 percent chance of completing this activity between 86 and 134 days. B. There is approximately a 68 percent chance of completing this activity between 98 and 122 days. C. There is approximately a 95 percent chance of completing this activity between 98 and 122 days. D. There is approximately a 75 percent chance of completing this activity between 86 and 134 days.
How do you communicate bad news in your team?
You are the project manager for a construction company that is building a new city and county office building in your city. Your CCB recently approved a scope change. You know that scope change might come about as a result of all of the following except: A. Schedule revisions B. Product scope change C. Changes to the agreed-upon WBS D. Changes to the project requirements