You are a project manager for a network cabling project for your organization. Your project team is made up of six full-time employees and three contractors. This is the first time they have all worked together. This project requires accurate information exchange at all times during the life of the project. How many lines of communication exist among the project team members?

A.36
B.41
C.18
D.34


No Answer is Posted For this Question
Be the First to Post Answer

Post New Answer

More Project Management Interview Questions

What are the skills required to be a project manager? Followup question, Rate yourself in each of the skill with examples.

18 Answers   Cognizant, Microsoft,


What are the different software reengineering activities?

0 Answers  


The amount of authority a project manager possesses can be related to: A. The project manager’s communication skills B. The organizational structure C. The amount of authority the manager of the project manager possesses D. The project manager's influencing skills

0 Answers  


What is the concept of project management?

0 Answers  


You are a project manager for an engineering company. Your company won the bid to add ramp-metering lights to several on-ramps along a stretch of highway at the south end of the city. You subcontracted a portion of the project to another company. The subcontractor's work involves digging the holes and setting the lamp poles in concrete. The subcontractor's performance is not meeting the contract requirements, because the poles are not buried to the correct depth. Which of the following is true? A. You are in the Quality Assurance process and have performed a quality audit to assure correctness of work. B. You are in the Scope Verification process and have performed a quality audit to assure correctness of work. C. You are in the Contract Administration process and have completed a contract audit to assure the subcontractor's performance meets the contract requirements. D. You are in the Performance Reporting process and have completed a performance review of the contractor's work.

0 Answers  






What are the different types of software risks?

0 Answers  


Which of the following is true regarding schedule variances? A. They impact scope, which impacts the schedule B. They sometimes impact the schedule C. They always impact the schedule D. They never impact the schedule

0 Answers  


All of the following are true about decomposition except: A. It's an output of the Scope Definition process. B. It's a tool and technique of the Scope Definition process. C. It is used to create a WBS. D. It subdivides the major deliverables into smaller components.

0 Answers  


You are the project manager for a large construction project. The project objective is to construct a set of outbuildings to house the Olympic support team that will be arriving in your city 18 months from the project start date. Resources are not readily available as they are currently assigned to other projects. Jack, an expert crane operator, is needed for this project two months from today. Which of the following skills will you use to get Jack assigned to your project? A. Negotiation and influencing skills B. Communication and organizational skills C. Communication skills D. Problem-solving skills

0 Answers  


You are the project manager working on a research project for a new drug treatment. Your preliminary project schedule runs past the due date for a federal grant application. The manager of the R&D department has agreed to release two resources to work on your project in order to meet the federal grant application date. This is an example of: A. Crashing B. Fast trucking C. Resource leveling D. Adjusting the resource calendar

0 Answers  


Your project's primary constraint is quality. In order to make certain the project team members don't feel too pressed for time and to avoid schedule risk, you decide to use which of the following activity estimating tools? A. Expert judgment B. Quantitatively based durations C. Reserve time D. Analogous estimating

0 Answers  


You are a project manager for Move It Now trucking company. Your company specializes in moving household goods across the city or across the country. Your project involves upgrading the nationwide computer network for the company. Your lead engineer has given you the following estimates for a critical path activity: 60 days most likely, 72 days pessimistic, 48 days optimistic. What is the expected value, or weighted average? A. 54 B. 66 C. 60 D. 30

0 Answers  


Categories