Which performance measurement is the cost of work budgeted for an activity within a certain time frame?
A. AV
B. PV
C. EV
D. EAC
No Answer is Posted For this Question
Be the First to Post Answer
Which of the following is displayed as an S-curve? A. Gantt B. Cost baseline C. Critical path D. PERT
You need to convey some very complex, detailed information to the project stakeholders. The best method of communicating this kind of information is? A. Verbal B. Vertical C. Horizontal D. Written
You are working on a project that is similar in scope to a project performed last year by your company. You might consider which of the following? A. Using the previous project's alternatives identification as a template B. Reusing the previous project's benefit/cost analysis as justification for this project C. Using the previous project's WBS as a template D. Reusing the previous project's product description when writing the scope statement
What are the tools and techniques used in the Initiation process? A. Project selection criteria, historical information, expert judgment B. Project selection methods, historical information, expert judgment C. Project selection criteria, expert judgment D. Project selection methods, expert judgment
Your company, Kick That Ball Sports, has appointed you project manager for their new Cricket product line introduction. This is a national effort, and all the retail stores across the country need to have the new products on the shelves before the media advertising blitz begins. The product line involves three new products, some with multiple deliverables. You are ready to create the WBS. Which of the following is true? A. The WBS should include the three new products and the advertising campaign as level two deliverables. B. The WBS should include the three new products as level two deliverables. C. The WBS should include the three new products as level two deliverables and the advertising campaign as a level three deliverable. D. The WBS should include the three new products and the advertising campaign as level three deliverables.
The purpose of the Initiation process is to: A. Formally recognize the existence of a project or project phase B. Formally recognize the need that brought about the project be it marketing demand, customer requests, business need, technological advances, or legal requirements C. Formally recognize the stakeholders of the project and identify them in the project charter D. Formally recognize the project sponsor and document his or her project goals
All of the following strategies are tools and techniques of Risk Response Planning used to reduce or control risk except? A. Mitigation B. Simulation C. Avoidance D. Acceptance
What are the outputs of the Scope Planning process? A. Product analysis, scope statement, and scope management plan B. Scope statement, scope management plan, and WBS C. Scope statement, supporting detail, and WBS D. Scope statement, supporting detail, and scope management plan
You are the project manager for Changing Tides video games. You have produced a project network diagram and have updated the activity list. Which process have you just finished? A. The Activity Sequencing process, which identifies all the specific activities of the project B. The Activity Sequencing process, which identifies all the activity dependencies C. The Activity Duration Estimating process, which diagrams project network time estimates D. The Activity Duration Estimating process, which identifies all the dependent activities of the project
You have been assigned to a project in which the objectives are to expand three miles of the north-south highway through your city by two lanes in each direction. You are interested in implementing a new project process called design-build in order to speed up the project schedule. The idea is that the construction team will work on the first mile of the highway reconstruction. At the same lime, the design team is coming up with plans for the third mile of the reconstruction rather than completing all design before any construction begins. This is an example of: A. Managing the projects as a program B. Fast tracking C. Progressive elaboration D. Collocation
You are a project manager for Laurel's theater productions. Your new project is coming in over budget and requires a cost change through the cost change control system. You know all of the following are true regarding Cost Control except: A. Performance is monitored to detect variances B. Changes are reflected in the cost baseline C. Changes are monitored and reflected in the project scope D. Changes are monitored so that inappropriate changes do not get into the cost baseline
You are a project manager for Dutch Harbor Consulting. Your latest project involved the upgrade of an organization's operating system on 236 servers. You performed this project under contract. You are in the Contract Closeout process and know that you should document: A. Lessons learned B. Performance measurements C. Formal acceptance D. Product verification