You are a project manager for a network cabling project for your organization. Your project team is made up of six full-time employees and three contractors. This is the first time they have all worked together. You know that the team will go through the stages of team development in the following order:
A. Forming, storming, norming, and performing
B. Storming, norming, forming, and performing
C. Norming, storming, forming, and performing
D. Forming, norming, storming, performing
No Answer is Posted For this Question
Be the First to Post Answer
Your upcoming project includes project team members from a foreign country. In order to make certain that cultural differences don't interfere with team performance, thereby affecting the success of the project, your first course of action is to do which of the following: A. Provide diversity training to all the team members. B. Collocate the project team. C. Perform team-building exercises. D. Inform the team members of the organization's rules and standards.
You are a project manager working on a new software product. Your company plans to market to businesses. The project sponsor told you that the project must be completed by September 1. The company plans to demo the new software product at a trade show in late September and therefore needs the project completed in time for the trade show. However, the sponsor has also told you that the budget is fixed at $85,000 and cannot be increased by even $10 due to overall budget cuts this year. You must complete the project within the given time frame and budget. Which of the following is the primary constraint for this project? A. Budget B. Quality C. Time D. Schedule
You are implementing a sap project. implementation compled and development started and at that time you found that there is major problem with the system .It would take again time and customer is not happy with that ,in that case how do you convince customer?
Why do you want to switch over from IT to management?
You’ve just accepted a new project management assignment. The project is for a customer in a foreign country. You've requested a business analyst and two other project team members from the country the customer resides in to participate on your team. The remaining team members are from your country. You know that the best way to ensure the project team doesn’t get bogged down in cultural differences and hold up project progress is to: A. Perform team-building exercises using videoconferencing to allow team members to get to know each other and get to the performing stage of team development as soon as possible. B. Provide diversity training for all the team members to make them aware of cultural differences and teach them to function effectively as a team despite these differences. C. Establish your role as project manager as the first order of business and require compliance to company policies. D. Require project team members to read and sign the organization’s diversity policy.
The project sponsor has approached you with a dilemma. The CEO announced at the annual stockholders meeting that the project you're managing will be completed by the end of this year. The problem is that this is six months prior to the scheduled completion date. It's too late to go back and correct her mistake, and stockholders are expecting implementation by the announced date. You must speed up the delivery date of this project. Your primary constraint before this occurred was the budget. What actions can you take to help speed up the project? A. Hire more resources to get the work completed faster. B. Ask for more money so that you can contract out one of the phases you had planned to do with in-house resources. C. Utilize negotiation and influencing skills to convince the project sponsor to speak with the CEO and make a correction to her announcement. D. Examine the project plan to see if there are any phases that can be fast tracked, and then revise the project plan to reflect the compression of the schedule.
You are developing your project schedule and have decided to use the PERT method to determine project duration. The estimates you've gathered so far include the following: Most likely is 200 hours, optimistic is 180 hours, and pessimistic is 220 hours. Which of the following is the correct PERT estimate? A. 190 B. 266 C. 200 D. 210
You are a project manager working on gathering requirements and establishing estimates for the project. Which process group are you in? A. Planning B. Executing C. Initiation D. Controlling
What change would you like to bring in the management of your previous organization ?
You know that PV = 475, AC = 430, EV = 480, EAC = 40, and BAC = 525. What is VAC? A. 440 B. 390 C. 485 D. 435
Your project team is a close group all busily working on project activities. They're close to approaching the performing stage of Team Development. All six members must communicate frequently with each other. How many lines of communication are there? A. 12 B. 15 C. 18 D. 14
You are a project manager for the information technology division of a local satellite TV broadcasting company. This spring, the chief information officer for your company gave you the project to convert and upgrade all the PCs in the department to the latest release of a specific desktop application. Prior to this conversion, all manner of desktop software existed on machines throughout the company and had caused increasing problems with sharing files and information across the company. A lot of unproductive hours were spent typing information into several formats. This project came about as a result of which of the following? A. Technological advance B. Business need C. Customer request D. Legal requirement