How you calculate
cement,sand,20mmbluemetal,40mmbluemetal,bricks for various
works
Answer / mohanraj
Gererally it is vary from ratio to ratio. For example C.C
1:2:4 for 20mm gravel. First we add all the ratios ie.,
1+2+4=7.then we divide individual ratio by total ratio and
multiply 1.57m3. Cement=1*1.57/7=.224m3.Sand =
2*1.57/7=.45m3 20mm gravel= 4*1.57/7=.90m3.For 40mm gravel
multiply with 1.52m3.
| Is This Answer Correct ? | 2 Yes | 3 No |
state the functional requirement of a retaining wall
what else we can add rather than admixture in concrete to reduce the cement quantity?
what is the difference between gypsum and pop?
What the approval that owner will give to contractor during construction project period? What will the affect on project if delays due approvals?
What are the steps involved in the concreting process?
How to make a c++ program that converts any base to base 10?
how we check the thickness and line of ceiling plaster.
at what height brick masonr, block masonry & Concrete wall can construct in a day ?
Difference b/w tor steel or tmt bar
What is progress payment?
how to decide cement quantity in 1 m3 concrete
How much steel required in one cubic meter RCC Main girder
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)