Gererally it is vary from ratio to ratio. For example C.C
1:2:4 for 20mm gravel. First we add all the ratios ie.,
1+2+4=7.then we divide individual ratio by total ratio and
multiply 1.57m3. Cement=1*1.57/7=.224m3.Sand =
2*1.57/7=.45m3 20mm gravel= 4*1.57/7=.90m3.For 40mm gravel
multiply with 1.52m3.
| Is This Answer Correct ? | 2 Yes | 3 No |
Post New Answer View All Answers
Explain moment of inertia and its importance.
Exterior Joints,define
Why is the statue of liberty made of copper?
How to plan a project
is there any thumb rule for calculating construction cost of the building with pile foundation per sft. area?
a solid steel rod length 2m dia and 20mm vertically hangs from celling and has a collar firmly atteched to it. above the collar an annular rubber washer of 40mm th. having stifness k = 5n/mm is placed. determine maximum stress in the rod caused by mass of 5 kg falling through a height of 1.2m.
I Want To Know Quantity of Cement Conc. & Sand in Column of 9"x9"x10'
what energized you to complete your course?
factory shed foundation l=4, b=3' d=8' rcc foudation for top to bottom pl tell me cement ,steel ,sand ,labour cost ,excavtion,soil is weak not so hard
Define What is the origin of name Railway Sleepers?
I am doing a engineering contract with GOI. I have purchased certain material from outside Maharashtra and paid CST on that material @ 5.25%. Please intimate whether I will be liable for VAT or VAT on works contract or not.
I what know about life time of frp tank plz explain about it specifications & other details
What is the absolute pressure scale?
How to calculate brick work quantity?? Block work quantity??
What do you understand by “preset” during the installation process of bridge bearings?