Answer / k.prakashchandra
Maintain a charging current of 10 A ,till charging current
becomes zero at 130% voltage.Then discharge after the
battery has cooled down, at the rate of 10A till the voltage
drops by 10%.Re- charge again before use.
| Is This Answer Correct ? | 0 Yes | 0 No |
why do MCB melt but not tripped in lighting highmast??
why neutral busbar size is half of the phase busbar size in control panels
why there is a phase difference between line voltage & phase voltage ?
What is MS-EXCELL?
why ac ratings are in tons?
Disadventage of cable-gland earthing if any ?
what is the write prosidure of stringing of 8meter pcc pole.
Cables Construction hi friends, 0.6/1/1.2 kV LV , DC and Control cables are concentric copper conductor what does its means and what is the use of concentric copper conductor,and are this with copper tape shield or copper screening, ? thanks
What is the importance of counter based plan & how is it scheduled?
should dc supply will give the transformer to build up the voltage level
what is power ratio between star & delta connection of 3 phase induction motor
why can not run two different phase circuit in to the same conduite
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)