For 1m3 wet volume concrete,1.57 m3 or 157% dry volume required if mix using 20 mm metal.
and 1.52 m3 or 152% dry volume required if mix using 40 mm metal.
This is based on Experimental Investigations arrived.
Is This Answer Correct ? | 1 Yes | 0 No |
Answer / shivakumara
Depending on the gradation of aggregate it varis from 40to
70 percent
Is This Answer Correct ? | 0 Yes | 0 No |
Answer / hassan bin mohsin
Dry volume consider of concrete
1.54 to 1.57 time dry volume of concrete
They for it considers 45% to 50% it increases in volume
Is This Answer Correct ? | 0 Yes | 0 No |
what"s the different between OPC (ordinary portland cement) and PPC (pozalana portland cement)?
3 Answers Ashok Leyland, Marathon Realty,
How much paint is required for 1sqm.?how to calculate the paint...?
1 Answers MRKR, Sumadhura Infracon,
can we find any technical issue if we are gong to change the dimensions of steel beams from one type to another type IE if there are any equievelant data base to find solution for problem of changeing sectios of beam from one type to another with the same cross sectional area.
what is the concrete grade for 1034.13N/mmsq
sir tell me the formula for calculating the volume of 380mm dia double under reamed pile of 4.0 mts depth.
how much sand requires for Light weight blocks for 100sqft
explain kn/sqm in detail.
the min diameter of steel used in footing are
how to determine pile length and diameter of pile is there any thumb rule?
How much is the cover for slab?
If drainage is main things then which respect the super Elevation may be provided?
230mm thick brick wall 10rmt length and 4.1 mtr high brick wall. tell quantity of cement,sand,brick required? Also tell me labour required to complete brickwall in 2days