Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


We have one 500KVA transformer. We have tested REF relay
and commissioned. After one and half year, due to some
ground fault in one of the DB circuit Transformer tripped
by REF relay. What will be cause and remedy. Please advise?



We have one 500KVA transformer. We have tested REF relay and commissioned. After one and half year..

Answer / k.prakashchandra

I think DB is the marshalling box.If there is earth fault
or short circuit in CT secondaries of REFR core ,as the
balancing of currents is lost, there will be tripping.You
are advised to test the Tr for internal earth fault before
re-charging.The coneections of CT leads in the MB TB may be
firmly done with brass/copper bolts and nuts to avoid loose
connections.

Is This Answer Correct ?    1 Yes 0 No

Post New Answer

More Electrical Engineering Interview Questions

rrb question

0 Answers  


how to size a diesel generator set?

1 Answers  


What is resolution of a measurement?

0 Answers  


What is the Different b\w Circuit Breaker & Isolater

11 Answers  


Show the schematic arrangement of diesel power station layout and give its principle of operation.

0 Answers  


What is the rating of circuit breaker needed for 300 KVA load in 33 KV supply line in a transformer of 33 KV / 415 Volt ?

0 Answers   Hira Group,


what is the function of impulse relay

0 Answers  


Difference between 3.5 core and 4 core

2 Answers  


Dear All, I am new in construction company , my boss ask a question at time of interview , If we have 60MW generation and Single Power Transformer step-up we have. if CMR 50/60MVA , ONAN, ONAF respectively , is it sufficient or not ? for that much power to transfer,

0 Answers  


how to connect generators in parallel and what are the required equipment to do so?

2 Answers   MSEB,


I have a transformer 3phase 11kv/410v and its name plate missing. now how can I judge its rated kva?

2 Answers   Coca Cola,


What is infinite Busbar?

4 Answers   Equate,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4456)
  • Electrical Engineering Interview Questions Electrical Engineering (16639)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)