What is aMilestone Confirmation
Answer / srsaru991
The milestone confirmation is a special form of
confirmation, in which the confirmation of one operation
causes other operations or suboperations to be
automatically confirmed at the same time.
Milestones are operations that have the corresponding
indicator in the control key.
Operations can be defined as milestone operations in their
control keys. If a milestone operation is confirmed, then
previous operations are automatically confirmed.
Is This Answer Correct ? | 16 Yes | 0 No |
Is it possible to assign user status to a sub-operation in maintenance order?
1)can we create a maintenance plan without planning the cost in it?
2 Answers Accenture, CSC, IBM, Ronak, Sabic,
Which t code can give you the list of all pending preventive maintenance order for the coming month?
I am a beginner in Sap pm.Can anyone suggest me some good website to know more abt sap pm module. If anyone has any material abt it, plz mail to my mail:-urskartik.a@gmail.com
Is it possible to trigger a notification from maintenance plan? How?
What level of functional locations should be changed for alternative labeling?
What is the order type for breakdown maintenance?
How to configure system to allow notification type change?
Which maintenance plan type is suitable for performing annul service of a car?
Explain the integration points between pm and mm/fico during the pm configuration?
What functions are determined by the category of the functional location?
Which of the following Master data is relevant for PM ? ( Bill of Material ,Customer Master , Functional Location ,Vendor Master ??)