1 cubic meter contains how many bricks
Answers were Sorted based on User's Feedback
Answer / santosh singh
hi,
1 cubic meter contains 500 bricks of size 20cm x20 cmx 10cm
this is standard.
if size of brick varies then u can find it like this
no. of bricks = total volume of work/ volume of one brick
| Is This Answer Correct ? | 888 Yes | 242 No |
Answer / daya
Hi ,
1 cubic meter contains 500 bricks
The Standard size of the 1st class brick is 190mm x 90mm x
90mm and motor joint should be 10mm thick
So brick with motor=200 x 100 x 100.
Volume of 1st class brick = 0.19 x 0.09 X 0.09 = 0.001539
cu.m
Volume of 1st class brick with motor =0.2 x 0.1 x 0.1=0.002
cu.m
No. on bricks per 1cu.m= 1/volume of 1st class brick with
motor
=1/0.002
= 500 nos of bricks
Volume of the 1st class brick = 500 x 0.001539
=0.7695 cu.m
Volume of the 1st class brick = 1-0.7695
= 0.2305 cu.m
| Is This Answer Correct ? | 366 Yes | 35 No |
Answer / pramansrivastava
as per CPWD norm icum contain 496 no. of brick of size
230mm X115mm X75mm.
| Is This Answer Correct ? | 308 Yes | 78 No |
Answer / m.ranjith kumar
IF THE STANDARD SIZE OF BRICK IS 190mm*90mm*90mm is,
Volume of 1 brick=0.19*.09*.09=0.001539cu.m
No. of bricks required for 1cu.m= 1/Volume of 1 brick
= 1/0.001539
= 649.77(appr 650 Nos.)
| Is This Answer Correct ? | 258 Yes | 124 No |
Answer / praman
as per CPWD norm icum contain 494 no. of brick of size
230mm X115mm X75mm.
| Is This Answer Correct ? | 139 Yes | 34 No |
Answer / anil kumar kushwaha
we should concentrate to the question.
(i)how many bricks contains 1 cum
(i)how many bricks contains 1 cum masonary....
then the answer will be diffrent for each question
| Is This Answer Correct ? | 62 Yes | 15 No |
Answer / anish bhimani
Hi ,
1 cubic meter contains 395 No. bricks
The Standard size of the brick is 230mm x 100mm x 75mm and mortar joint should be 12mm thick
So, brick with mortar= 242 x 112 x 86mm.
No. of Bricks per 1 C.mt.= 1/volume of brick with mortar
=1/.002330944
= 430 No. of bricks
So, Net Brick Quantity = 430 No. + 20 NO. Wastage = 450 No.
| Is This Answer Correct ? | 71 Yes | 25 No |
Answer / kamlesh mahajan
volume of 1 brick is 0.002cum so no. of brick
is 1/0.002=500 No.
| Is This Answer Correct ? | 50 Yes | 4 No |
can u plz send me ntpc placement papers(civil engineering) at munjalricha1988@gmail.com and which types of questions are aked by ntpc
For 1 cu m of concrete required 1.54 Cu m times dry volume. Pl give clarification of 1.54 factor
1 Answers RASA, Unity Infraprojects,
factory shed foundation l=4, b=3' d=8' rcc foudation for top to bottom pl tell me cement ,steel ,sand ,labour cost ,excavtion,soil is weak not so hard
What is Rodding?
What are the tests to be conducted on cement?
what is difference between active and passive earth pressure. how it effect the retaining wall design ?
How to fix steel in rectangular footins? I.e first along the length or first along the width??
deshuttering time for RCC for DPC over the foundation.
IS STEEL BARS IS AS PER ISI TRANSVERSE RIBS SHOULD BE UNIFORM IN DISTANCE, PLEASE EXPLAIN WHY,
what is fineness modulas of sand ?
Why we test compressive strength after 28 days..?
3 Answers NM Caramoan Builders,
Pl let me know approx. Rcc construction cost per sq.Foot for Building a house with2800 sqfeet carpet area in pune city
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)