Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

1 cubic meter contains how many bricks

Answer Posted / anish bhimani

Hi ,
1 cubic meter contains 395 No. bricks

The Standard size of the brick is 230mm x 100mm x 75mm and mortar joint should be 12mm thick
So, brick with mortar= 242 x 112 x 86mm.


No. of Bricks per 1 C.mt.= 1/volume of brick with mortar
=1/.002330944
= 430 No. of bricks

So, Net Brick Quantity = 430 No. + 20 NO. Wastage = 450 No.

Is This Answer Correct ?    71 Yes 25 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

cement, sand, aggregate,reinforcement & concrete consumption per square feet in multi storeyed building

2387


Mention what are the composition of a landfill?

1093


Why steel rods are produced only in even dimensions?

2554


how to calculate Rate of analysis for 100 m3 Any ratio of concrete ? including labour

1531


how much need cement bags for block work of wall approx 1000 hollow blocks 20x20x40cm

2062


sir tell me the formula for calculating the volume of 380mm dia double under reamed pile of 4.0 mts depth.

1940


how much cement and sand required for 100sqm of wall plastering in different proportions

2336


the volume of cement req for 70cum of brickwork in 1:6 cement mortar is approx is equal to 3cum 5cum 7cum 1ocum

1990


in levelling operation the first site on any change point is back site the second site on any change point is fore site the line commenses with fore sight & closes with backsight the line comensses with back sight & closes with fore sigh

2226


please give me the rates of RCC(CUM), PCC(CUM), Brick Work(CUM), Tile Flooring, Saria Shuttering

1515


in the earthquqke the profile of water on dam is parabolic or not

1907


Does VDF add strength to the flooring apart from preventing water ingress?

1520


IS code for Rolling Margin of steel

2410


Method of findingthe dry ingredient quantity of 1 m3 concrete. what is the difference between static and dynamic induced emf? Testing charges bill given for Rs. 32,000/- but not added service tax in this bill. So, How much TDS will be deduct

1434


what is meant by residual strain?

2277