For Beams sides only 1 day
For coloumns 1 day
For slabs span<4.50m 7 days
For slabs span>4.50m 14 days
| Is This Answer Correct ? | 14 Yes | 0 No |
Post New Answer View All Answers
How to calculate(Thumb rule) the consumption of steel per cubic meter for different concrete members.
What is meant by Crystal Concrete?
How to calculate plastering for elevated water storage tank
Hi how r u ? hope you are fine there . Please can u tell me tha Design life of Buildings as Per ACI CODE 318-99. It will be a pleasure for me .Thanks in advance
suppose that 156000 sq.ft rcc work builtup are.how many % of brick work to rcc work.
Where can I get a Text Book on Design of Blast Resistant Buildings in PDF form.
1. What is coefficient use for calculation of shuttering. 2. What is coefficient use for calculation of reinforcement in one cum of concrete.
What is absolute coordinates?
2nd and 4rt angle elevation used in which country ?
What are the responsibilities of a construction manager?
If we have the center line of the Finnish road level and we want to know what level of pay would have offset the Lhs and Rhus RHS 1,2.5,5 1,2.5,5 m.
Tell me about triple point of water.
Can inverted beams used in pipes during construction?
Why should appointment store person for project ? what is the benefits for company ?
What is Critical path in Ms-Project ?