Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


What is the difference between lap splice length and
development length of rebars?

Answers were Sorted based on User's Feedback



What is the difference between lap splice length and development length of rebars?..

Answer / sjtbehera

Lap splice length is recquired to transfer force from one
bar to another bar.
Devolpment length is embadded lenght of reinforcement
recquired to develop the design sterngth of the
reinforcement.

Is This Answer Correct ?    68 Yes 2 No

What is the difference between lap splice length and development length of rebars?..

Answer / aung

lap splice is the length require to transfer stress in
reinforcement and development length is the additional
length required to get enough bond strength between steel
and concrete.

Is This Answer Correct ?    39 Yes 3 No

What is the difference between lap splice length and development length of rebars?..

Answer / c.kumar

Splice length is required prior to transfer the load from one bar to another bar and also to minimize the Bending Moment but the develoment length is added to reinforcement in order increase the R.C.C design and bonding strength b/w steel & concrete.

Is This Answer Correct ?    3 Yes 0 No

What is the difference between lap splice length and development length of rebars?..

Answer / kamlesh chauhan

both the words technically same,only usage is different.

Is This Answer Correct ?    10 Yes 38 No

Post New Answer

More Civil Engineering Interview Questions

1 cum of 60*25*25 block cost 187 dirhams. Find the cost of 1 sqm of block ?

1 Answers   BPO, Vastu Vihar,


4. What is your philosophy / attitude towards work?

6 Answers  


shape of aggregates used in concrete should be rounded/cubical or elongated/flaky.

9 Answers  


Maximum foundation pressure under PRCC box is 19 T/Sqm and net safe bearing capacity is 12.65. Is it safe? pl help me

1 Answers   Indian Railways,


WHAT IS THE CAUSES OF RUTTING ON FLEXIBLE PAVEMENT?

0 Answers   Ace Info, Anil Group,


What is the Specific gravity of cement?Water?

9 Answers  


why construction joint in the slab should be l/3 of span? what's the technical reason for that?

1 Answers  


In how many types u can do POP on ceiling and walls(on which material or by using which material)? b) what is the difference between dry , oil bound, enamel, acrlyic type of painting? 2nd :- I have certain queries, please help to solve. a) length of pile bore is 4m.excavation quantity will be area * length where area will be pi/4 * dia*dia. Is this right? b) It is a single reamed pile of 300m dia and reamed dia is 750mm. can any body help me to calculate excavated quantity of this bulb(reamed section),, concrete quantity in bulb with showing the formulas to be used?

0 Answers  


How do we determine the specific gravity of a cement?

0 Answers  


Can any colleague send me the steel frame pictures of roofs, beams, columns, footings, roof bends, door bends etc. I shall be very gratefull.Suhail_akhter@hotmail.com

0 Answers  


How to calculate paint drums per meter square

0 Answers   Speco,


the coefficient of curvature for a well graded soil must be inthe guage 0.5-1 3-4 4-5 none

1 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4456)
  • Electrical Engineering Interview Questions Electrical Engineering (16639)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)