A 150KW 440V motor is need to replace in the field instead
of faulty one. what are the main parameter should I need to
check?



A 150KW 440V motor is need to replace in the field instead of faulty one. what are the main parame..

Answer / a.p.nanjappa

150kw , 440 is a large motr. the starting current of this
induction motor will be 5-8 times depend on drive ex-fan.
and coast for 6-8s to attain full speed.
so, the new contactor shall be good quality , with
overload,instantaneous with time delay shall be selected.
Reverse rotation protection, vibrations,
Unbalnced current protection optional.
LV power cable terminal box cable connection and support.

Is This Answer Correct ?    0 Yes 0 No

Post New Answer

More Electrical Engineering Interview Questions

Can Anyone suggest the Standards (IEC or IS) for selecting copper current density?

0 Answers  


how can we select the rating of Load break switch that is connected to the primary protection of 200 kva 11kv/415v distribution transformer?? step by step calculated answr pls...thnk.u

2 Answers   Maruti Suzuki,


Please tell me ceilingfan sweep means. Commenly we used sweep1200mm and 600mm MMENLY WE USED CEILINGFAN SWEEP1200MM AND SWEEP600MM

1 Answers  


what is ATS?and its function or operation in power system with its layout.

1 Answers   DLF,


Why no-load primary current is very small as compared to full load current in transformer (as 1% of full load current?

5 Answers   NTPC,






what happens if dc supply is given and the remedies for it.

0 Answers  


HOW TO CALCULATE SINGLE PHASE AMPERES IN 3 PHASE TRANSFORMER? GIVE AN EXAMPLE PLZZZ

1 Answers  


HOW many type of Circut Breaker in the world used in 400 kv substation?

14 Answers   Power Grid,


If I fill the form of engineering services and I left the exam de to navoidable reasons . Will it counts my one attempt

2 Answers  


Why we are use 11KV / 22KV / 33KV / 66KV / 110KV / 230KV / 440KV this type of ratio. why cant we use other voltage ratio like 54KV / 99KV et.,

8 Answers   College School Exams Tests, Hino, ITC Infotech, Reliance, UPRVUNL,


Please brief working principle & construction of permanent magnet AC Servo motor

0 Answers   DRJ ARDE,


Can we use generator transformer as step down transformer? How?

3 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4452)
  • Electrical Engineering Interview Questions Electrical Engineering (16638)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)