Answer / anil
as per indiaqn standards the bars above 32mm dia bars are
to be welded not lapped. its a twisting questions in
interviews
| Is This Answer Correct ? | 37 Yes | 0 No |
Answer / ashok yadav
Lap length is depends on various factors such as grade of
concrete used, load on the structures and economical
criteria.
| Is This Answer Correct ? | 0 Yes | 1 No |
Answer / irwin
Since the 36 mm dia bar is subject to compression, hence the the formula for the required lap is L=37(d)
where;
d=36
L=37(36)
L=1,332 (minimumn required lap for compression)
| Is This Answer Correct ? | 0 Yes | 2 No |
Answer / sjtbehera
yes 50 dia of bars in thumb rule. but when you are going to
calculated it is diffrence in compression and tension zone.
| Is This Answer Correct ? | 3 Yes | 6 No |
Answer / mahendra mohan srivastava
Lap length will 50 d here d is dia of the bar.
and anchroge length will 58d. after 25d lap length will
joint through welding joint.
| Is This Answer Correct ? | 1 Yes | 4 No |
Answer / sudhir patil
Actually its depend upon the design & grade of concrete.Its
normal practice to take 50 times of the diameter of steel
hence for 36 mm dia bar it should be taken 1800 mm.
| Is This Answer Correct ? | 4 Yes | 7 No |
What is the difference between tor steel and tmt steel?
Difference b/w tor steel or tmt bar
Describe Briefly The Various Methods Of Concrete Curing?
what is injection grouting and what is rewiring.
Give me the name of type of slabs?
What is construction mitigation management?
How much quantity water should be placed in one cubic meter area?
What are the effects of water on shear strength and foundations?
I've one slab of 24m x 43m. How to calculate required steel For this slab.
we are roofing contractors,we are filling a bill in work contract 4.12% method, we collecting 4.12% from our customer but every month we have been paying the vat at 2% from our pocket on the total value of bill. our auditor told me the above method do not collect 2% from the customer side is it true?
Sir your company in receiver ment of civil engineering.
WHAT do mean by M-309
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)