i have a bar of 36 dia in column, what is the lap length?
Answer Posted / sudhir patil
Actually its depend upon the design & grade of concrete.Its
normal practice to take 50 times of the diameter of steel
hence for 36 mm dia bar it should be taken 1800 mm.
| Is This Answer Correct ? | 4 Yes | 7 No |
Post New Answer View All Answers
03. a. The water cement ratio for achieving maximum strength of concrete is…… 1 b. Water/ cement is inversely proportional to-------------- 1 c. Increasing the slump decreases the strength: True / false 1
step by step procedure to find out the percentage of steel in coloum,beam,slab,footing in detailed
SAND AND STONE AGGREGATES WASTAGE PERCENTAGE IN CONCRETING WORK?
What is the difference between undo & redo?
If density of cement is 1500 Kg/m3, the how is specific gravity 3.15 ? (Density of water is 1000 Kg/m3)
Explain creep?
Can we use Polystyrene as a Bitumen modifier !! if so is it a good MS research topic ? and what type of laboratory tests will be conducted during Research work ??
how many litres of enamel paint required for 5000 sft of site??
How many times we can use Fresh bentonite ford wall execution? Would like to know the clear concept of recycling. After flushing can we use it for another time time for flushing? Or we have to use it for for excavation only?
How to hide dimensions in autocad?
what is the soil bearing capacity for a 5 floor multistorey residential building and which type of soil ? what is plinth beam? in wall load calculation center to center column distance is considered or not/
what is the cost differene of a same structure when it is constructed with brick masonary, and when it is constructed with concrete as a frame structure.????????
What is thumb rule in quality and quantity estimation of a Residential building??
cement required for construction of 400mm*200mm*200mm concrete solid blocks for 1sq.mtrs,how?
I have certain queries, please help to solve. a) length of pile bore is 4m.excavation quantity will be area * length where area will be pi/4 * dia*dia. Is this right? b) It is a single reamed pile of 300m dia and reamed dia is 750mm. can any body help me to calculate excavated quantity of this bulb(reamed section),, concrete quantity in bulb with showing the formulas to be used?