Answer / dinesh sharma
Cement :1> visual test : check for lumps if have then
rejected.2> cement sample rub in finger pour if feel
granular then its not fit for construction.
Aggregate : looking round in shape and flakiness percentage
in not more then 20%.
Water : clear visual(transprency,not durty) and potable in
taste
Fine Aggregate : 1> take a sample and placed in test tube
or in any transperent flask etc. and add water leave for
half an hour and see fine agg.is settled down and silt and
other impurities in upper part.
2> New sample rub between hands if hands are durty means
sample is not fit.
answer of sofia is for concrete not for cement kindly
update sofia.
| Is This Answer Correct ? | 59 Yes | 1 No |
Answer / sachin
cement:- colour of cement should be greenish gray, it
should have no slumps, it should flot 4 some time when
sprinkelled on stell water, when hands are put inside the
cement hands should get the sence of collness.
aggregates:-coarse aggreagets when sieved should retained
on 4.75 mm sieve and it shouild get pass on 8mm sieve.
fine aggregates should pass through 4.75 mm sieve, if taken
in hands and hands are clossed cumps should not be formed.
water:- i dont think there is any field test 4 water. but
as far as possible it should be clean.
| Is This Answer Correct ? | 15 Yes | 4 No |
Answer / sharan c b
cement:- colour of cement should be greenish gray, it
should have no slumps, it should flot 4 some time when
sprinkelled on stell water.
1> take a sample and placed in test tube
or in any transperent flask etc. and add water leave for
half an hour and see fine agg.is settled down and silt and
other impurities in upper part.
2> New sample rub between hands if hands are durty means
sample is not fit.
water:- i dont think there is any field test 4 water. but
as far as possible it should be clean.
| Is This Answer Correct ? | 7 Yes | 1 No |
Answer / ganesh
salty water is not suitable for the construction, pl
notedown
| Is This Answer Correct ? | 5 Yes | 0 No |
how much bentonite powder mix in 1000ltr fresh water with detail.
what is two point problem.
plz tell me max persantage of sand for every mix design by volume or weight.
What is the minimum size of the particles of silt soil?
How many materials e.g bricks, cement, sand, stone required to build a house for 100 sqft
Generally construction is based on which method:limit state of working stress
3 Answers Mars Planning Engineering Services, Sterling Wilson,
how to calculate steel quantity in plinth beam&footing
Characteristics of a model project are ––
If drainage is main things then which respect the super Elevation may be provided?
Brick size 230X115X150mm, how many bricks, quantity of sand, cement required to construct 10 sq mtrs of 115mm thick brick wall.
For 12mm thick and cement plastering 1:6 on 100sqm new Brick work the quantity of cement required is
what is the specification for silt content in sand
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)