please tell me the all the spcications of the 100MW 11KV
HYDEL POWER PLANT SPECICATIONS
Answers were Sorted based on User's Feedback
Answer / shanth
its a 100 mW power plant switch gear is 11kv.how we can use
11kv sysytem for a 100mw planrt it will result in huge
losses.any way to answer this question it would be 200MVA
transformer and 11kv siwtch gear
Is This Answer Correct ? | 0 Yes | 0 No |
Answer / digambar
1.rated current
2.sc capacity
3.sc capasity withstand time
4.cable sizing
Is This Answer Correct ? | 1 Yes | 3 No |
Which type of gas used in cylinder (VCB)?????
what is acceptance test in electrical engineering.
If the neutral wire go pass through the core balance current transformer? If yes then why? and no then why?
If Three Runs of 1Cx300 Sqmm Cable between Transformer and VCB and the distance between 100mtrs. what will be total length of Cable and if cost 1500Rs per meter,what would be the total cost
how load of a turbo generator can be increased
What is meant by cold loop test in instrument
why do you add the load short circuit impedance when considering short circuit amperage. It seems that you should only consider supply. If you need to consider loads and you don't know what loads are to be added , what would be a good sub-transient reactance rating for the loads?
break down of electricity is more in summer or in winter ? give reason
Plugging is a phenomenon to= A braking the motor B to accelerate the motor C to run IM as generator D to start the motor
what is the effect of constant power factor to the voltage regulation
factor to be considered for bus bar design
what is a reactive power? what is the relation with power factor?