TO operate transformers in parallel, vector symbol of the
both should be same.If one transformer name plate is not
there, how can we conclude that whether the transformer is
having the same vector symbol or not?

Answers were Sorted based on User's Feedback



TO operate transformers in parallel, vector symbol of the both should be same.If one transformer n..

Answer / guru

Check the vector group by carrying out VECTOR Group testing
( By Injecting a 3 Ph 440v or 230 V to the primary windings
and check the voltage between the terminals in secondary
side)

For each vector group there are standard values which has
to come in the secondary side

Is This Answer Correct ?    1 Yes 0 No

TO operate transformers in parallel, vector symbol of the both should be same.If one transformer n..

Answer / rajendran

we can easily find out and confirm the vector group of the
transformer by using the standard test procedures.

Is This Answer Correct ?    3 Yes 3 No

TO operate transformers in parallel, vector symbol of the both should be same.If one transformer n..

Answer / mgalalkhedr

This vector group test is done at site to check if their is
any damage in the windings during transportation and
erection.
3 -phase AC supply is given on HV side. R-Phase HV and r-
phase LV shorted.

Then to qualify the test following conditions are to be
satisfied after measurement of voltages.

nR+nY=RY, By>> Bb and Yb=Yy.

Is This Answer Correct ?    0 Yes 0 No

TO operate transformers in parallel, vector symbol of the both should be same.If one transformer n..

Answer / mahboob

in such acase we can find the vector group by conducting
vector group test the we can proceed

Is This Answer Correct ?    1 Yes 2 No

Post New Answer

More Electrical Engineering Interview Questions

What is Black-out and Brown-out situation in the context of voltage stability in power system?

1 Answers  


what is the differnce between high impedance relay and low impedance relay

4 Answers   Areva,


I am getting above 60 V as open delta voltage against single phase unit ICT at tertiary delta formed and ICT getting trippped on NDR. ICT tested and found in order. PTs provided on tertiary are tested and in order. what may be the reason?

1 Answers  


Why indicated only R.Y.B to phase.

6 Answers   Bhel,


what are the safety of chiller.

7 Answers  


how to calculate transformer turn primary & secondary side 11kv to 420v

0 Answers  


what is the minimum insulation resistance for HT AND LT motor ?

3 Answers  


What is class X ct? What rare its uses?

2 Answers  


If ROC does not lies inside unit circle,then ? a) Fourier transform converges b) Z transform converges c) Hatly transform converges d) Colpit Transform converges.

0 Answers   CCP,


why most of the substations are rated in multiples of 11?

4 Answers  


mounting of bucholz relay engle on transformer

4 Answers  


how gen. load increase or decrease ? what happen with gen on that time

2 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4452)
  • Electrical Engineering Interview Questions Electrical Engineering (16637)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)