The process of selecting suitable ingredients of concrete
and determining their relative amounts with the objective
of producing a concrete of the required, strength,
durability, and workability as economically as possible, is
termed the concrete mix design.
Requirements of concrete mix design
The requirements which form the basis of selection and
proportioning of mix ingredients are :
a ) The minimum compressive strength required from
structural consideration
b) The adequate workability necessary for full compaction
with the compacting equipment available.
c) Maximum water-cement ratio and/or maximum cement content
to give adequate durability for the particular site
conditions
d) Maximum cement content to avoid shrinkage cracking due
to temperature cycle in mass concrete.
Is This Answer Correct ? | 0 Yes | 0 No |
Answer / a.jagadesh
Mix design is to get a compressive strength of rcc cube to
20n/mm2 or above.
Is This Answer Correct ? | 0 Yes | 0 No |
Answer / mohammed essam
as per the design, a load is given and the strength of concrete is being provided to the ready mix company, for ex M800, It implies that the structure requires a concrete capable of taking load upto 800N/mm2, the ready mix company mix ADMIXTURES such as fly ash, rise husk etc. its known as the design mix
Is This Answer Correct ? | 1 Yes | 2 No |
Answer / bharani.r
mix the ingredients of concrete like cement, aggregates,
water as per code given for given component like 1:2:4, etc.,
Is This Answer Correct ? | 7 Yes | 9 No |
Answer / sanjay kumar chatterjee
Mix design is a design mix that is made to acquire the
required strength as per particular requirement, the ratio
should be such that if 200Kg/cm2 is required than M20 is to
be designed, it is not a simple ratio mix of 1:2;4
or1;1.5:3 it depends on many factors
Is This Answer Correct ? | 1 Yes | 3 No |
Answer / gadevinilkumar
what is new version of concrete mix design s.p.36 or not
Is This Answer Correct ? | 1 Yes | 4 No |
Answer / sudhakar.a
It is the process to determining the ingredients of
concrete like cement,sand and aggregate in order of
proportion (i.e)1:2:4,1:3:6,1:4:8,1:5:10
Is This Answer Correct ? | 0 Yes | 5 No |
Answer / pari
to find the amound of cement ,sand,coarse aggregate for
perticular ratio(like 1:2:4).
Is This Answer Correct ? | 5 Yes | 11 No |
how many cement use for 1cum concrete for 25Grade.
What is bending moment
HOw much % of premium on DSR-2013 currently
what is bending moment, for simply supported slab ? how do you calculate ?
what is conrete grade ,how are depent on concrete grad and size of concrete?
explain how to calculate top and bottom diagonals for transimission line tower foundation with prop setting
Difference between Hydro Pneumatic and Gravity system of water supply in a building?
why spacer in reinforcement?
curing of concrete why 7day's,14day's 21day's 28days
what is the cost difference of a same structure when it is constructed with brick masonary and when it is constructed with block masonary and concrete as a frame structure????????????????????????
how much cement,sand,aggregate will use for 1 cum in ratio of 1:2:4.
16 Answers ARS, College School Exams Tests, Gulf Construction, HRL, mWorkspace, NCC, URC Construction,
providing, fixing, removal of pockets of size 100*150*300mm to 500*600*1000mm for foundation. the shuttering material used for making &fixing of pockets shall be removed by the contractor without damaged to pockets. if any damage occurred, the same shall be rectified by the contractor is to handover the pockets to forge shop engineer with proper marking of centre lines, levels etc.