In the field and in the control room different power
supplies if used How to handle the ground



In the field and in the control room different power supplies if used How to handle the ground..

Answer / banerjeenandan

Normally there should be different grounds in control room.
DCS or PLC vendor generally gives the drawing.

Mostly it is taken as convension that there should be 3
different grounding busbars in control room.

1. One is for the power earth. This will give the earthing
to the power distribution panel of the DCS or PLC.

2. Second is the Signal earth. All the shield cables will be
connected to this earthing busbar to minimize the
interference in the analog signal cables.

3. Thrd is Panel earth. This will be connected to the panel
body.

All these 3 busbars should be connected to 3 different
earthpits by 3 different Copper cables. Redundancy of
earthpits or copper cables may be there if possible.

Is This Answer Correct ?    3 Yes 1 No

Post New Answer

More Instrumentation Interview Questions

in rotark mov in display err msg showing how to remove the error

1 Answers  


i have one tank of 500mm height, which is in under vacuum of 735 mmHg, I want measure level of the same using DPT , SO WHAT WILL BE THE URV & LRV, DENSITY OF THE TANK FLUID IS 0.95. is there necessary to fill the LP side with fluid.

7 Answers  


What is live zero and dead zero

2 Answers  


How 2 calibrate level tank having large height..?

2 Answers  


Anybody know how to create a ladder programme for power switch in TV remote without using counter... ie TV can be turn on and turn off using single push button switch... on pressing the switch first time TV turn on and hold the on state till i press the switch again, and after TV turn off.

2 Answers  






what are the selections available in configuring a burnout protection of a controller? thanks

0 Answers   NPC Alliance Corporation,


Transducer Input 0 to 230 v ac Output-0 to 10vdc Receiver Input 0 to 10 vdc and Output 4 to 20 ma How?

1 Answers  


how to calculate the temp. of RTD&Thermocouple when we got some mV r Ohms?if anybody has d chart pls mail the chatrs to me...

1 Answers  


I want condensate pots vent position erection of flow transmitter ?

1 Answers  


what does a positioner in control valve ?

11 Answers  


Can we use twisted pair cable instead of ethernet for communication?

1 Answers   Yokogawa,


WHAT ARE MAIN DIFFERENCE BETWEEN DCS AND SCADA?

7 Answers   ABB, Gold Fields, Rand Water,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)