Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

In the field and in the control room different power
supplies if used How to handle the ground

Answer Posted / banerjeenandan

Normally there should be different grounds in control room.
DCS or PLC vendor generally gives the drawing.

Mostly it is taken as convension that there should be 3
different grounding busbars in control room.

1. One is for the power earth. This will give the earthing
to the power distribution panel of the DCS or PLC.

2. Second is the Signal earth. All the shield cables will be
connected to this earthing busbar to minimize the
interference in the analog signal cables.

3. Thrd is Panel earth. This will be connected to the panel
body.

All these 3 busbars should be connected to 3 different
earthpits by 3 different Copper cables. Redundancy of
earthpits or copper cables may be there if possible.

Is This Answer Correct ?    3 Yes 1 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

What is Positive Calibration and Negative Calibration?

2180


How to Calibrate Level Troll in field

1337


WHAT IS TMXT IN TEMPERATURE FOUNDATION FIELDBUS.

2251


Q- What are the application in which PNP transistor is preferred over NPN ?

3288


How you calibrate absolute pressure with the calibration range of 0 to 1000 0C Absolute. Please explain the procedure for calibration.

1646


What is defferent betwen ESP &PCP PUMP .HOW IT IS WORK?

2417


Draw bode plot of any transfer function. Why is plotting bode necessary?

2432


Explain signal isolator

1094


what is your eligibility criteria for freashers?

2076


what is interlock system and why we use of this?

1962


In power plant to measure vibration of a turbine we install sensors. Before install this sensor we have to set gap voltage. What is meant by gap voltage and its use?

2025


what is installation and commissioning of (fat & sat) of power plant dcs ? this question keeps in desirable conditions of one company .

4795


Capacitance, resistance ( colour coding ), parallel & series circuits.

2163


What is modbus?

1132


can anyone tell me about the basic concepts to consider before to start a PLC panel wiring

1870