Who fixes the bug as Severity and priority ?

Answers were Sorted based on User's Feedback



Who fixes the bug as Severity and priority ?..

Answer / j

Test Engineer

Is This Answer Correct ?    9 Yes 1 No

Who fixes the bug as Severity and priority ?..

Answer / suman

severity by tester and priority by team lead

Is This Answer Correct ?    3 Yes 0 No

Who fixes the bug as Severity and priority ?..

Answer / aashish

serverity is decided by test engineer
and priority is decide by project manager

Is This Answer Correct ?    3 Yes 1 No

Who fixes the bug as Severity and priority ?..

Answer / reddy

It depends upon organization to organization. Anyone can
assign bug's severity and priority if he knows rules within
the project. Rules are decided mutually between
Developement and QA teams. You can find out with your team
member or your immediate boss about the practise. Generally
team lead will assign or modify the severity & priority of
the bug to avoid confusion.

Is This Answer Correct ?    2 Yes 0 No

Who fixes the bug as Severity and priority ?..

Answer / karnati sreedhar

Severity Will be Fix by Test Engineer or Test Lead From
Testing Dept
Priority Will be Fix by Defect Tracking Team
Project Manager or Sr.From Developement Dept Or Sr.From
Testing Dept Or Some Times Client Also Fix the Bug(If the
Client is Familer with the Project)

Is This Answer Correct ?    2 Yes 1 No

Who fixes the bug as Severity and priority ?..

Answer / senthilkumar

TEst leader only know how much that bug effect the
application...so he only assign sevearity status....

Is This Answer Correct ?    1 Yes 0 No

Who fixes the bug as Severity and priority ?..

Answer / sunil

severity is set by tester.
priority is set by developer.

Is This Answer Correct ?    1 Yes 0 No

Who fixes the bug as Severity and priority ?..

Answer / keshab

It depends entirely on the size of the company. Severity
tells us how bad the defect is. Priority tells us how soon
it is desired to fix the problem.
In some companies, the defect reporter sets the severity
and the triage team or product management sets the
priority. In a small company, or project (or product),
particularly where there aren't many defects to track, you
can expect you don't really need both since a high severity
defect is also a high priority defect. But in a large
company, and particularly where there are many defects,
using both is a form of risk management.

Is This Answer Correct ?    1 Yes 1 No

Who fixes the bug as Severity and priority ?..

Answer / shrinivas poodari

Seviority is fixed by the project manager or test lead and
priority is fixed by the senior test engineer/test engineer
or if the "client" is famailier with the application then
that situations may client is also involved to fixed the
seviority and priority.

Is This Answer Correct ?    1 Yes 2 No

Who fixes the bug as Severity and priority ?..

Answer / ashwini

Project Manager

Is This Answer Correct ?    0 Yes 3 No

Post New Answer

More Manual Testing Interview Questions

What is the difference between santity & smoke testing?

6 Answers   Logica CMG,


DESCRIBE s/w quality assurence &s/w quality control

6 Answers   Accenture,


Which is the best book to ref. for design the test cases/scenario in manual testing,which gives detailed idea with all the strategies ?

2 Answers   Satyam,


How to write gui test cases ? plz gve me some sugessition about gui test cases along with examples plz plz any one plz

3 Answers   CSE, TCS,


What are joins and subjoins in the data bases what is data driven testing what is verification and validation What is Quality Assurance (QA) and Quality Control (QC) Is Verification is related to QA and Validation is related to QC ? which type of model you follow basically in your project what is a use case How to test a Bike how to test a Lift (Elevator). which configuration Management tool do you use which Bug tracking tool do you use explain Bug life cycle what is Regression testing what is ALPHA testing ans BETA testing What types of testings comes under Non functional testing what is TEST DIRECTOR what is CMM and CMM i whar are Expressions in Winrunner What is a Compile module Is it Necessary to open the tool first or the application first after getting a bug what will you do if you add a new object or a new module for the existing application then how will you test the application which Defect tracking tool do you use what is change management What is smoke Testing what is sanity testing A application is given to you but the requirements and functionalities are missing what will you do to start the testing which testing documents will be received by the client

0 Answers   Mphasis, Netxcell,






what is the difference between V model and Waterfall model used in SDLC?

10 Answers  


Did anyone have any experince with stocking in equity can you please tell me how to approach the project.I am a learner.help me please.give me ur suggestions.

0 Answers   CTS, Oracle,


what is authorization & authentication?

2 Answers  


Hi all. I have 2 years exp in manual testing.Now i want to shift.i got so many email from other company that send ur cv .After sending no response from them .whats the reason.

1 Answers  


What is comparison testing?

4 Answers  


if you have a test cases please send me on singhajay7786@gmail.com thanks in advance.

0 Answers  


what is the role of QA manager

1 Answers  


Categories