If you know expected value is 500 and the standard deviation is 12, you can say with approximately a 95 percent confidence rating which of the following?
A. The activity will take between 488 and 512 days.
B. The activity will take between 464 and 536 days.
C. The activity will take between 494 and 506 days.
D. The activity will take between 476 and 524 days.


No Answer is Posted For this Question
Be the First to Post Answer

Post New Answer

More Project Management Interview Questions

The theory that 85 percent of the cost of quality is a management problem is attributed to: A. Doming B. Kaizen C. Juran D. Crosby

0 Answers  


Explain the difference between risk and issues?

0 Answers  


You are a project manager for Dutch Harbor Consulting. Your latest project involved the upgrade of an organization’s operating system on 236 servers. You performed this project under contract. You are in the Closing process and know that product verification is for what purpose? A. To verify the goals of the project and assure the product of the project is complete B. To evaluate all the work of the project and compare results to project scope C. To verify all the work was completed correctly and satisfactorily D. To evaluate project goals and assure the product of the project meets the requirements

0 Answers  


You are the project manager for the Late Night Smooth Jazz Club chain, with stores in 12 states. Smooth Jazz is considering opening a new club in Kansas City or Spokane. You have derived the following information: Project Kansas City: The payback period is 27 months, and the IRR is 35 percent. Project Spokane: The payback period is 25 months, and the IRR is 32 percent. Which project should you recommend to the selection committee? A. Project Spokane because the payback period is shortest B. Project Kansas City because the IRR is highest C. Project Spokane because the IRR is lowest D. Project Kansas City because the payback period is longest ?

0 Answers  


Common causes of variances are a result of all of the following except: A. Random variances B. Predictable variances C. Special variances D. Variances that are always present in the process

0 Answers  






Your project selection committee used a weighted scoring model and found that Project B, with a score of 54, should be chosen over the other competing projects. Which of the following is true? A. Weighted scoring models are a benefit measurement method, which is a tool and technique in the Initiation process. B. Weighted scoring models are a constrained optimization method, which is an output of the Initiation process. C. Weighted scoring models are a constrained optimization method, which is a tool and technique in the Initiation process. D. Weighted scoring models are a benefit measurement method, which is an output of the Initiation process.

0 Answers  


What are the qualities of a good project manager?

0 Answers  


What are the initiation process outputs? A. Project charter, identification and assignment of project manager, constraints, and project overview documents B. Project charter, project overview, feasibility study, and constraints C. Project charter, identification and assignment of project manager, constraints, and assumptions D. Identification and assignment of project manager, project overview, constraints, and assumptions

0 Answers  


Many times software delivery is late, why? Give reason.

0 Answers  


Explain the concept of total quality management.

0 Answers   EX,


why is ITIL certification required? what is the use of ITIL foundation certification?

4 Answers  


Your project was just completed. Due to some unfortunate circumstances, the project was delayed causing cost overruns at the end of the project. Which of the following is true? A. You document the circumstances as lessons learned. B. You pay particular attention to archiving the financial records for this project. C. Your project ended due to starvation because of the cost overruns. D. You document the circumstances surrounding the project completion during the Scope Verification process.

0 Answers  


Categories